16222 W COMMUNITY CT 91343

Certificate Information: 16222 W COMMUNITY CT 91343

Application / Permit
20010-20000-02766
Plan Check / Job No.
B20VN10498
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 50'-10" X 30'-3" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED PORCH
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
CofO Issued on 11/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 SELLA BENYAMIN
Corrections Issued 8/24/2020 SELLA BENYAMIN
Building Plans Picked Up 8/24/2020 APPLICANT
Plan Check Approved 3/3/2021 SELLA BENYAMIN
Issued 4/12/2021 APPLICANT
CofO in Progress 11/2/2022 RAUL OLAGI
CofO Issued 11/3/2022 MICHAEL SMITH
Permit Finaled 11/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/20/2020 ADRIAN CASTRO
Construction near power lines Cleared 12/18/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 12/29/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 1/6/2021 ROBERT DUFF
Low Impact Development Cleared 1/15/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/15/2021 ADRIAN CASTRO
Private sewage disp. approval Cleared 2/16/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/17/2021 Partial Approval ARTHUR SARGSYAN
Footing/Foundation/Slab 5/20/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 6/1/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 8/31/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 8/31/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 8/31/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/31/2021 Corrections Issued JENNIFER RABUCHIN
Special/Order Compliance 8/31/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/10/2021 Corrections Issued JACK KARGODORIAN
HVAC-Rough 9/10/2021 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 9/10/2021 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 9/10/2021 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Approved JACK KARGODORIAN
Insulation 9/30/2021 Approved JACK KARGODORIAN
Interior/Exterior Lathing 9/30/2021 Partial Approval JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 9/30/2021 Approved JACK KARGODORIAN
ELECTRICAL-Rough 10/26/2021 Corrections Issued ALAN MORELOS
ELECTRICAL-Rough 11/8/2021 Approved RAUL OLAGI
Wood Frame 11/8/2021 Approved RAUL OLAGI
Drywall Nailing 11/24/2021 Approved ALAN MORELOS
Sewer 2/4/2022 Corrections Issued RAUL OLAGI
Shower Pan 2/9/2022 Approved ALAN MORELOS
Sewer 2/16/2022 Approved RAUL OLAGI
Underground Mechanical 2/16/2022 Partial Approval RAUL OLAGI
Interior/Exterior Lathing 2/22/2022 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 2/22/2022 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 2/28/2022 Approved RAUL OLAGI
Underground Mechanical 2/28/2022 Corrections Issued RAUL OLAGI
Underground Mechanical 4/5/2022 Partial Approval RAUL OLAGI
Gas Test 6/7/2022 Partial Approval ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 8/23/2022 SGSOV Not Ready RAUL OLAGI
BUILDING-Rough-Frame 10/4/2022 Approved RAUL OLAGI
ELECTRICAL-Final 10/4/2022 Corrections Issued RAUL OLAGI
Final 10/4/2022 Corrections Issued RAUL OLAGI
Green Building Final 10/4/2022 Approved RAUL OLAGI
Green Building Rough 10/4/2022 Approved RAUL OLAGI
HVAC-Final 10/4/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 10/4/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 10/4/2022 SGSOV Not Ready RAUL OLAGI
Service/Power Release 10/4/2022 Not Ready for Inspection RAUL OLAGI
Smoke Detectors 10/4/2022 Approved RAUL OLAGI
Verify Sprinkler Sign Off 10/4/2022 Approved RAUL OLAGI
ELECTRICAL-Final 10/18/2022 Corrections Issued RAUL OLAGI
HVAC-Final 10/18/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 10/18/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Approved RAUL OLAGI
ELECTRICAL-Final 11/2/2022 Approved RAUL OLAGI
Final 11/2/2022 OK to Issue CofO RAUL OLAGI
HVAC-Final 11/2/2022 Approved RAUL OLAGI
PLUMBING-Final 11/2/2022 Approved RAUL OLAGI
Service/Power Release 11/2/2022 Approved RAUL OLAGI