254 N BRISTOL AVE 90049

Certificate Information: 254 N BRISTOL AVE 90049

Application / Permit
20010-20000-02765
Plan Check / Job No.
B20VN10497
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 81'6"X76'0" IRREGULAR SHAPED 2-STORY SFD WITH ATTACHED 23'6"X31'6" IRREGULAR SHAPED 3-CAR GARAGE, 12'0"X28'7-1/2" REAR TRELLIS, AND 12'0"X17'0" DECK ON TOP OF 1ST FLOOR. NFPA 13 D FIRE SPRINKLERS REQUIRED THROGUHOUT ***SEE COMMENTS (CONDITIONS TO BE COMPLIED WITH PRIOR TO CofO BEING ISSUED)***
Permit Issued
Issued on 3/19/2021
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 MARVEL DELACRUZ
Corrections Issued 9/1/2020 MARVEL DELACRUZ
Quality Review Completed 9/3/2020 STEVEN KIM
Building Plans Picked Up 9/4/2020 APPLICANT
Applicant returned to address corrections 1/19/2021 MARVEL DELACRUZ
Applicant returned to address corrections 1/21/2021 MARVEL DELACRUZ
Applicant returned to address corrections 3/3/2021 MARVEL DELACRUZ
Plan Check Approved 3/9/2021 MARVEL DELACRUZ
Plan Check Approved 3/11/2021 MARVEL DELACRUZ
Issued 3/19/2021 APPLICANT
CofO in Progress 10/19/2022 JUAN VALENZUELA
Permit Finaled 10/28/2022 DANIEL ORRANTE
CofO Issued 10/28/2022 DANIEL ORRANTE
Permit Finaled 10/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/22/2020 MATTHEW CRAIG
Address approval Cleared 12/31/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/6/2021 DINAH GARIN
Sewer availability Cleared 1/6/2021 DINAH GARIN
Low Impact Development Cleared 2/4/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/9/2021 DINAH GARIN
GPI Written Notices Cleared 3/9/2021 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 3/9/2021 MARVEL DELACRUZ
Green Code Cleared 3/9/2021 MARVEL DELACRUZ

Contact Information

Contractor A M G Capital; Lic. No.: 1040753-B 4911 GENISTA AVE      ENCINO, CA 91316
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/4/2021 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 5/14/2021 Approved JUAN VALENZUELA
Footing/Foundation/Slab 5/14/2021 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/2/2021 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 7/8/2021 Corrections Issued JUAN VALENZUELA
HVAC-Rough 7/8/2021 Approved JUAN VALENZUELA
PLUMBING-Rough 7/8/2021 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 7/12/2021 Not Ready for Inspection PIERRE VEGA
PLUMBING-Rough 7/12/2021 Partial Approval PIERRE VEGA
BUILDING-Rough-Frame 7/22/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 7/22/2021 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 7/22/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 7/22/2021 Corrections Issued JUAN VALENZUELA
Shower Pan 7/22/2021 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 7/22/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 7/29/2021 Approved JUAN VALENZUELA
Green Building Rough 7/29/2021 Approved JUAN VALENZUELA
PLUMBING-Rough 7/29/2021 Approved JUAN VALENZUELA
Insulation 8/2/2021 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/3/2021 Partial Approval KRISTEN CAUSEY
Interior/Exterior Lathing 8/4/2021 Approved KRISTEN CAUSEY
Insulation 8/5/2021 Partial Inspection KRISTEN CAUSEY
Drywall Nailing 8/13/2021 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 8/16/2021 Approved JUAN VALENZUELA
Gas Test 4/5/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 6/21/2022 Corrections Issued JUAN VALENZUELA
HVAC-Final 6/21/2022 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 6/27/2022 Corrections Issued BRENDAN LOONEY
HVAC-Final 6/27/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Final 6/27/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 7/1/2022 Approved JUAN VALENZUELA
HVAC-Final 7/1/2022 Approved JUAN VALENZUELA
PLUMBING-Final 7/1/2022 Approved JUAN VALENZUELA
Service/Power Release 7/26/2022 Approved KENNETH NAGLE
Final 9/23/2022 Corrections Issued JUAN VALENZUELA
Green Building Final 9/23/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 9/23/2022 Approved JUAN VALENZUELA
Final 10/14/2022 OK to Issue CofO JUAN VALENZUELA