10634 N HAYVENHURST AVE 91344

Certificate Information: 10634 N HAYVENHURST AVE 91344

Application / Permit
20010-20000-02748
Plan Check / Job No.
B20VN10479
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 20' X 30'(2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/25/2021
Issuing Office
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 SELLA BENYAMIN
Corrections Issued 9/17/2020 SELLA BENYAMIN
Quality Review Completed 9/18/2020 STEVEN KIM
Building Plans Picked Up 9/18/2020 APPLICANT
Plan Check Approved 1/26/2021 SELLA BENYAMIN
Issued 2/25/2021 APPLICANT
CofO in Progress 11/15/2022 JAVIER RAMOS JR
CofO in Progress 11/15/2022 JAVIER RAMOS JR
Permit Finaled 11/19/2022 MICHAEL SMITH
CofO Issued 11/19/2022 MICHAEL SMITH
Permit Finaled 11/19/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/22/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 9/28/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 10/13/2020 MATTHEW CRAIG
Low Impact Development Cleared 11/23/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/3/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/18/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/31/2021 Partial Approval MARK JOHNSON
Excavation/Setback/Form/Re-Bar 4/12/2021 Not Ready for Inspection MARK JOHNSON
Excavation/Setback/Form/Re-Bar 4/21/2021 Approved MARK JOHNSON
Wood Frame 5/4/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 9/28/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/28/2021 Corrections Issued JENNIFER RABUCHIN
Gas Test 9/28/2021 Partial Approval JENNIFER RABUCHIN
Green Building Rough 9/28/2021 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 9/28/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 9/28/2021 Corrections Issued JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 9/28/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Not Ready JENNIFER RABUCHIN
Verify Sprinkler Sign Off 9/28/2021 Approved JENNIFER RABUCHIN
Wood Frame 9/28/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/21/2021 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 10/21/2021 Approved MARK JOHNSON
Gas Test 10/21/2021 Partial Approval MARK JOHNSON
HVAC-Rough 10/21/2021 Partial Approval MARK JOHNSON
PLUMBING-Rough 10/21/2021 Approved MARK JOHNSON
Rough-Elec/Plmb/HVAC 10/21/2021 Approved MARK JOHNSON
Shower Pan 10/21/2021 Not Ready for Inspection MARK JOHNSON
Wood Frame 10/21/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 11/2/2021 Partial Approval MARK JOHNSON
Interior/Exterior Lathing 11/17/2021 Partial Approval JACK KARGODORIAN
Shower Pan 11/17/2021 Approved JACK KARGODORIAN
Drywall Nailing 12/10/2021 Approved MARK JOHNSON
Insulation 12/10/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 12/10/2021 Not Ready for Inspection MARK JOHNSON
Interior/Exterior Lathing 12/28/2021 Approved BRENDAN LOONEY
Sewer 1/31/2022 Approved JESUS RODRIGUEZ
Gas Test 2/4/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 2/4/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 4/7/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 6/17/2022 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 10/4/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 10/4/2022 Approved JAVIER RAMOS JR
Final 10/4/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 10/4/2022 Approved JAVIER RAMOS JR
Green Building Final 10/4/2022 Approved JAVIER RAMOS JR
HVAC-Final 10/4/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 10/4/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/4/2022 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 10/4/2022 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 10/4/2022 Approved JAVIER RAMOS JR
Final 11/15/2022 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 11/15/2022 Approved JAVIER RAMOS JR