10634 N HAYVENHURST AVE 91344
Certificate Information: 10634 N HAYVENHURST AVE 91344
- Application / Permit
- 20010-20000-02748
- Plan Check / Job No.
- B20VN10479
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 20' X 30'(2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/25/2021
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/17/2020 | SELLA BENYAMIN |
| Quality Review Completed | 9/18/2020 | STEVEN KIM |
| Building Plans Picked Up | 9/18/2020 | APPLICANT |
| Plan Check Approved | 1/26/2021 | SELLA BENYAMIN |
| Issued | 2/25/2021 | APPLICANT |
| CofO in Progress | 11/15/2022 | JAVIER RAMOS JR |
| CofO in Progress | 11/15/2022 | JAVIER RAMOS JR |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 9/28/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 10/13/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/23/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/3/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/31/2021 | Partial Approval | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 4/12/2021 | Not Ready for Inspection | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 4/21/2021 | Approved | MARK JOHNSON |
| Wood Frame | 5/4/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 9/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 9/28/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 9/28/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 9/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 9/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 9/28/2021 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 9/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/21/2021 | Corrections Issued | MARK JOHNSON |
| ELECTRICAL-Rough | 10/21/2021 | Approved | MARK JOHNSON |
| Gas Test | 10/21/2021 | Partial Approval | MARK JOHNSON |
| HVAC-Rough | 10/21/2021 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 10/21/2021 | Approved | MARK JOHNSON |
| Rough-Elec/Plmb/HVAC | 10/21/2021 | Approved | MARK JOHNSON |
| Shower Pan | 10/21/2021 | Not Ready for Inspection | MARK JOHNSON |
| Wood Frame | 10/21/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 11/2/2021 | Partial Approval | MARK JOHNSON |
| Interior/Exterior Lathing | 11/17/2021 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 11/17/2021 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 12/10/2021 | Approved | MARK JOHNSON |
| Insulation | 12/10/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 12/10/2021 | Not Ready for Inspection | MARK JOHNSON |
| Interior/Exterior Lathing | 12/28/2021 | Approved | BRENDAN LOONEY |
| Sewer | 1/31/2022 | Approved | JESUS RODRIGUEZ |
| Gas Test | 2/4/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 2/4/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 4/7/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 6/17/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/4/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 10/4/2022 | Approved | JAVIER RAMOS JR |
| Final | 10/4/2022 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/4/2022 | Approved | JAVIER RAMOS JR |
| Green Building Final | 10/4/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 10/4/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 10/4/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 10/4/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 10/4/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 10/4/2022 | Approved | JAVIER RAMOS JR |
| Final | 11/15/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 11/15/2022 | Approved | JAVIER RAMOS JR |