5938 N CORBIN AVE 91356

Certificate Information: 5938 N CORBIN AVE 91356

Application / Permit
20010-20000-02735
Plan Check / Job No.
B20VN10457
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 97' X 51' 6" IRREGULAR SHAPED SINGLE FAMILY DWELLING WITH ATTACHED COVERED PATIO ALL WORK PER ENGINEERING NFPA 13D FIRE SPRINKLERS REQUIRED
Permit Issued
Issued on 4/1/2021
Issuing Office
Current Status
CofO Issued on 10/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 9/2/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 9/3/2020 OMID HEDAYAT
Building Plans Picked Up 9/14/2020 APPLICANT
Applicant returned to address corrections 3/18/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 3/25/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/1/2021 SEWADA ZADOORAN MILAGARDI
Issued 4/1/2021 APPLICANT
CofO in Progress 7/27/2022 SEAN HAUPT
CofO Issued 10/25/2022 JOHN JANSON
Permit Finaled 10/25/2022 JOHN JANSON

Permit Application Clearance Information

Permit Cleared 9/24/2020 ADRIAN CASTRO
Address approval Cleared 9/25/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/25/2020 ADRIAN CASTRO
Sewer availability Cleared 9/25/2020 ADRIAN CASTRO
Trees in Parkway Cleared 10/20/2020 JOHN KIM
Hydrant and Access approval Cleared 11/10/2020 KURT CORRAL
Low Impact Development Cleared 12/31/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/31/2020 GUILLERMO PETRA
Certificate of Compliance Cleared 1/27/2021 MARC WOERSCHING

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/8/2021 Partial Inspection STEVEN BACK
PLUMBING-Rough 4/15/2021 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 4/21/2021 Approved STEVEN BACK
Footing/Foundation/Slab 4/28/2021 Approved STEVEN BACK
Special/Order Compliance 4/28/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 5/12/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Partial Approval STEVEN BACK
Green Building Rough 5/12/2021 Not Ready for Inspection STEVEN BACK
Verify Sprinkler Sign Off 5/12/2021 Not Ready for Inspection STEVEN BACK
Deputy Reinf. Concrete 6/3/2021 Approved STEVEN BACK
ELECTRICAL-Rough 6/3/2021 Approved STEVEN BACK
HVAC-Rough 6/3/2021 Approved STEVEN BACK
PLUMBING-Rough 6/3/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 6/9/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Corrections Issued STEVEN BACK
Green Building Rough 6/9/2021 Not Ready for Inspection STEVEN BACK
Verify Sprinkler Sign Off 6/9/2021 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 6/24/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Approved STEVEN BACK
Green Building Rough 6/24/2021 Not Ready for Inspection STEVEN BACK
Verify Sprinkler Sign Off 6/24/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 6/28/2021 Approved STEVEN BACK
Green Building Rough 6/28/2021 Approved STEVEN BACK
Interior/Exterior Lathing 6/28/2021 Partial Approval STEVEN BACK
Shower Pan 6/28/2021 Corrections Issued STEVEN BACK
Verify Sprinkler Sign Off 6/28/2021 Approved STEVEN BACK
Insulation 7/1/2021 Corrections Issued SHAVONNE ESPINOZA
Insulation 7/6/2021 Approved STEVEN BACK
Interior/Exterior Lathing 7/6/2021 Approved STEVEN BACK
Shower Pan 7/6/2021 Approved STEVEN BACK
Drywall Nailing 7/15/2021 Approved RYAN SALAZAR
Gas Test 1/27/2022 Not Ready for Inspection SEAN WIRCH
Gas Test 2/3/2022 Partial Inspection JUSTIN HAWLEY
ELECTRICAL-Final 3/24/2022 Approved SEAN HAUPT
HVAC-Final 3/24/2022 Corrections Issued SEAN HAUPT
PLUMBING-Final 3/24/2022 Approved SEAN HAUPT
Final 6/8/2022 Corrections Issued SEAN HAUPT
Green Building Final 6/8/2022 Approved SEAN HAUPT
HVAC-Final 6/8/2022 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 6/8/2022 SGSOV Not Ready SEAN HAUPT
Service/Power Release 6/8/2022 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 6/8/2022 Approved SEAN HAUPT
Final 7/26/2022 OK to Issue CofO SEAN HAUPT
HVAC-Final 7/26/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 7/26/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 7/26/2022 Approved SEAN HAUPT