17821 W VALERIO ST 91335

Certificate Information: 17821 W VALERIO ST 91335

Application / Permit
20010-20000-02702
Plan Check / Job No.
B20VN10397
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19'10" X 29'8" TWO STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (E), ALL WORK PER ENGINEERING - SEE COMMENTS
Permit Issued
Issued on 12/20/2021
Issuing Office
Current Status
CofO Issued on 1/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 RARES BODEA
Corrections Issued 9/1/2020 RARES BODEA
Quality Review Completed 9/11/2020 STEVEN KIM
Building Plans Picked Up 9/14/2020 APPLICANT
Plan Check Approved 11/4/2021 RARES BODEA
Issued 12/20/2021 APPLICANT
CofO in Progress 1/10/2023 JEFFREY BULL
CofO Issued 1/25/2023 JOHN JANSON
Permit Finaled 1/25/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/16/2020 ADRIAN CASTRO
Permit Cleared 10/16/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/24/2020 ADRIAN CASTRO
Sewer availability Cleared 11/24/2020 ADRIAN CASTRO
Low Impact Development Cleared 1/25/2021 MARTIN FRAGOSO
Trees in Parkway Cleared 3/31/2021 JOHN KIM
Roof/Waste drainage to street Cleared 5/4/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/23/2022 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 3/2/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 3/2/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/8/2022 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 3/8/2022 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 3/8/2022 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 3/14/2022 Partial Approval VINCENT HANLEY
Insulation 3/14/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 3/14/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 4/18/2022 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/18/2022 Approved VINCENT HANLEY
HVAC-Rough 4/18/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 4/18/2022 Partial Approval VINCENT HANLEY
Wood Frame 4/18/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/22/2022 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 4/28/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/28/2022 Approved VINCENT HANLEY
Green Building Rough 4/28/2022 Approved VINCENT HANLEY
HVAC-Rough 4/28/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/28/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 4/28/2022 Approved VINCENT HANLEY
Insulation 5/12/2022 Approved VINCENT HANLEY
Drywall Nailing 5/20/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 5/20/2022 Approved MORRIS JACKSON
Final 9/27/2022 Corrections Issued JEFFREY BULL
Green Building Final 9/27/2022 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV Approved JEFFREY BULL
Service/Power Release 9/27/2022 Not Ready for Inspection JEFFREY BULL
Smoke Detectors 9/27/2022 Approved JEFFREY BULL
Final 1/10/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 1/10/2023 Approved JEFFREY BULL
Service/Power Release 1/10/2023 Approved JEFFREY BULL