17821 W VALERIO ST 91335
Certificate Information: 17821 W VALERIO ST 91335
- Application / Permit
- 20010-20000-02702
- Plan Check / Job No.
- B20VN10397
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 19'10" X 29'8" TWO STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (E), ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 12/20/2021
- Issuing Office
- Current Status
- CofO Issued on 1/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | RARES BODEA |
| Corrections Issued | 9/1/2020 | RARES BODEA |
| Quality Review Completed | 9/11/2020 | STEVEN KIM |
| Building Plans Picked Up | 9/14/2020 | APPLICANT |
| Plan Check Approved | 11/4/2021 | RARES BODEA |
| Issued | 12/20/2021 | APPLICANT |
| CofO in Progress | 1/10/2023 | JEFFREY BULL |
| CofO Issued | 1/25/2023 | JOHN JANSON |
| Permit Finaled | 1/25/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/16/2020 | ADRIAN CASTRO |
| Permit | Cleared | 10/16/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/24/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 1/25/2021 | MARTIN FRAGOSO |
| Trees in Parkway | Cleared | 3/31/2021 | JOHN KIM |
| Roof/Waste drainage to street | Cleared | 5/4/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/23/2022 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 3/2/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/2/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/8/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Rough | 3/8/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 3/8/2022 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/14/2022 | Partial Approval | VINCENT HANLEY |
| Insulation | 3/14/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 3/14/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/18/2022 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/18/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 4/18/2022 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 4/18/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/22/2022 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/28/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/28/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/28/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/28/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/28/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/28/2022 | Approved | VINCENT HANLEY |
| Insulation | 5/12/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/20/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 5/20/2022 | Approved | MORRIS JACKSON |
| Final | 9/27/2022 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 9/27/2022 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 9/27/2022 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 9/27/2022 | Approved | JEFFREY BULL |
| Final | 1/10/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 1/10/2023 | Approved | JEFFREY BULL |
| Service/Power Release | 1/10/2023 | Approved | JEFFREY BULL |