5117 N ENCINO AVE 91316

Certificate Information: 5117 N ENCINO AVE 91316

Application / Permit
20010-20000-02679
Plan Check / Job No.
B20VN10338
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25.5'X37' DETACHED ACCESSORY DWELLING UNIT (788 SQ. FT.) PER GCS 6585.2.2(e)(1)(B) ***NFPA-13D FIRE SPRINKLERS REQUIRED***
Permit Issued
Issued on 10/1/2020
Issuing Office
Current Status
CofO Issued on 7/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 COLIN LOREDO
Corrections Issued 8/20/2020 COLIN LOREDO
Quality Review Completed 8/21/2020 OMID HEDAYAT
Building Plans Picked Up 8/25/2020 APPLICANT
Applicant returned to address corrections 9/30/2020 COLIN LOREDO
Plan Check Approved 10/1/2020 COLIN LOREDO
Issued 10/1/2020 APPLICANT
CofO in Progress 7/21/2021 DAVID SANDOVAL
Permit Finaled 7/22/2021 JOHN JANSON
CofO Issued 7/22/2021 JOHN JANSON
Permit Finaled 7/22/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/26/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/26/2020 GABRIEL ROBLES
Sewer availability Cleared 8/26/2020 GABRIEL ROBLES
ZA Case Cleared 8/31/2020 PABLO ESTRADA
Hydrant and Access approval Cleared 9/15/2020 KURT CORRAL
Low Impact Development Cleared 9/25/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/28/2020 GABRIEL ROBLES
Green Code Cleared 9/29/2020 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/5/2020 Approved STEVEN BACK
Footing/Foundation/Slab 10/5/2020 Approved STEVEN BACK
PLUMBING-Rough 10/5/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/30/2020 Partial Approval STEVEN BACK
Gas Test 1/6/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 1/6/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 1/6/2021 Approved BRENDAN LOONEY
Gas Test 1/19/2021 Partial Inspection BRENDAN LOONEY
HVAC-Rough 1/19/2021 Approved BRENDAN LOONEY
Shower Pan 1/19/2021 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 1/25/2021 Partial Approval HENRY KIM
ELECTRICAL-Rough 1/25/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/25/2021 Approved HENRY KIM
Green Building Rough 1/25/2021 Not Ready for Inspection HENRY KIM
Shower Pan 1/25/2021 Approved HENRY KIM
Verify Sprinkler Sign Off 1/25/2021 Approved HENRY KIM
BUILDING-Rough-Frame 1/29/2021 Approved HENRY KIM
ELECTRICAL-Rough 1/29/2021 Approved HENRY KIM
Green Building Rough 1/29/2021 Approved HENRY KIM
Interior/Exterior Lathing 1/29/2021 Approved HENRY KIM
Drywall Nailing 2/9/2021 Approved STEVEN BACK
Insulation 2/9/2021 Approved STEVEN BACK
Underground Mechanical 4/9/2021 Approved STEVEN BACK
ELECTRICAL-Final 6/1/2021 Not Ready for Inspection STEVEN BACK
HVAC-Final 6/1/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Final 6/1/2021 Approved STEVEN BACK
Final 7/13/2021 Corrections Issued STEVEN BACK
Green Building Final 7/13/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/13/2021 SGSOV Approved STEVEN BACK
Service/Power Release 7/13/2021 Approved STEVEN BACK
Smoke Detectors 7/13/2021 Approved STEVEN BACK
Final 7/16/2021 Not Ready for Inspection STEVEN BACK
Final 7/20/2021 OK to Issue CofO DAVID SANDOVAL
Service/Power Release 7/20/2021 Approved DAVID SANDOVAL