7459 N IRVINE AVE 91605
Certificate Information: 7459 N IRVINE AVE 91605
- Application / Permit
- 20010-20000-02675
- Plan Check / Job No.
- B20VN10310
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (20'X30' , 1200 SQ. FT.) ACCESSORY DWELLING UNIT PER LAMC 12.22 A33 (c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | COLIN LOREDO |
| Corrections Issued | 9/3/2020 | COLIN LOREDO |
| Quality Review Completed | 9/28/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 9/30/2020 | APPLICANT |
| Applicant returned to address corrections | 10/27/2020 | COLIN LOREDO |
| Applicant returned to address corrections | 2/1/2021 | COLIN LOREDO |
| Plan Check Approved | 2/11/2021 | COLIN LOREDO |
| Issued | 2/19/2021 | APPLICANT |
| CofO in Progress | 7/20/2022 | JOHN HAYES |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
| CofO Issued | 8/24/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 12/31/2020 | MARTIN FRAGOSO |
| Sewer availability | Cleared | 1/14/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/25/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 2036 CREEK RD KITTY HAWK, NC 27949 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2021 | Approved | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 5/11/2021 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 6/4/2021 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 7/21/2021 | Approved | DANIEL DREW |
| Wood Frame | 8/10/2021 | Partial Approval | DANIEL DREW |
| Wood Frame | 8/12/2021 | Partial Approval | DANIEL DREW |
| Wood Frame | 8/17/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Partial Approval | DANIEL DREW |
| Wood Frame | 9/20/2021 | Not Ready for Inspection | DANIEL DREW |
| Deputy Wood Construction | 10/21/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 10/25/2021 | Approved | MISAEL ESPARZA |
| Wood Frame | 10/25/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/28/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Wood Frame | 10/28/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 11/1/2021 | Corrections Issued | DANIEL DREW |
| PLUMBING-Rough | 11/1/2021 | Partial Approval | DANIEL DREW |
| Wood Frame | 11/1/2021 | Corrections Issued | DANIEL DREW |
| HVAC-Rough | 11/10/2021 | Approved | MISAEL ESPARZA |
| Wood Frame | 11/10/2021 | Approved | MISAEL ESPARZA |
| Insulation | 11/16/2021 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/16/2021 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/19/2021 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 11/24/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/24/2021 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 12/20/2021 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 12/23/2021 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 12/28/2021 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 12/28/2021 | Corrections Issued | JACK KARGODORIAN |
| Structural Steel Frame | 12/28/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Underground Mechanical | 12/30/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/13/2022 | Approved | MATT KELLERMAN |
| Final | 6/13/2022 | Corrections Issued | MATT KELLERMAN |
| Footing/Foundation/Slab | 6/13/2022 | Approved | MATT KELLERMAN |
| Green Building Final | 6/13/2022 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Not Ready | MATT KELLERMAN |
| Service/Power Release | 6/13/2022 | Corrections Issued | MATT KELLERMAN |
| Smoke Detectors | 6/13/2022 | Approved | MATT KELLERMAN |
| Verify Sprinkler Sign Off | 6/13/2022 | Approved | MATT KELLERMAN |
| ELECTRICAL-Final | 7/11/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/11/2022 | Corrections Issued | JOHN HAYES |
| HVAC-Final | 7/11/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 7/11/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 7/11/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 7/18/2022 | Conditional Approval | DAVID MATSON |
| Final | 7/18/2022 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Final | 7/18/2022 | Approved | DAVID MATSON |
| PLUMBING-Final | 7/18/2022 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | DAVID MATSON |
| Service/Power Release | 7/18/2022 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 7/20/2022 | Approved | JOHN HAYES |
| Final | 7/20/2022 | OK to Issue CofO | JOHN HAYES |
| HVAC-Final | 7/20/2022 | Approved | JOHN HAYES |
| PLUMBING-Final | 7/20/2022 | Approved | JOHN HAYES |
| Service/Power Release | 7/20/2022 | Approved | JOHN HAYES |