11933 W ADDISON ST 91607

Certificate Information: 11933 W ADDISON ST 91607

Application / Permit
20010-20000-02669
Plan Check / Job No.
B20VN10267
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-4" x 20'-2" ONE STORY DETACHED ACCESSORY DWELLING UNIIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
Issued on 4/12/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/2/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 SEAN SHAHMIRI
Corrections Issued 9/28/2020 SEAN SHAHMIRI
Quality Review Completed 9/29/2020 OMID HEDAYAT
Building Plans Picked Up 10/1/2020 APPLICANT
Applicant returned to address corrections 3/1/2021 SEAN SHAHMIRI
Plan Check Approved 3/19/2021 SEAN SHAHMIRI
Applicant returned to address corrections 3/23/2021 SEAN SHAHMIRI
Issued 4/12/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/6/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 10/7/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 10/7/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 11/3/2020 MATTHEW CRAIG
Miscellaneous Cleared 1/20/2021 DANG NGUYEN
ZI Cleared 1/20/2021 ANDREW JORGENSEN
ZI Cleared 1/20/2021 ANDREW JORGENSEN
Low Impact Development Cleared 3/16/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/16/2021 GABRIEL ROBLES

Contact Information

Contractor Conquest General Building Contractors Inc; Lic. No.: 460741-B DBA CONQUEST QUALITY POOLS   2215 FIRST STREET #101    SIMI VALLEY, CA 93065
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/26/2021 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 5/4/2021 Approved THOMAS FINNILA
Deputy Wood Construction 6/1/2021 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/1/2021 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 7/15/2021 Conditional Approval THOMAS FINNILA
HVAC-Rough 7/15/2021 Approved THOMAS FINNILA
PLUMBING-Rough 7/15/2021 Partial Approval THOMAS FINNILA
Shower Pan 7/15/2021 Not Ready for Inspection THOMAS FINNILA
Wood Frame 7/15/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 7/23/2021 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 7/23/2021 Approved THOMAS FINNILA
Green Building Rough 7/23/2021 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 7/23/2021 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 7/23/2021 Conditional Approval THOMAS FINNILA
Insulation 8/19/2021 Corrections Issued LILIANA PORTILLO
Insulation 8/20/2021 Conditional Approval LILIANA PORTILLO
Drywall Nailing 8/24/2021 Approved THOMAS FINNILA
Green Building Rough 8/24/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/24/2021 Conditional Approval THOMAS FINNILA
Insulation 9/9/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/9/2021 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 9/13/2022 No Access for Inspection ALAN MORELOS
Final 9/13/2022 No Access for Inspection ALAN MORELOS
Green Building Final 9/13/2022 No Access for Inspection ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 9/13/2022 SGSOV Not Ready ALAN MORELOS
Service/Power Release 9/13/2022 No Access for Inspection ALAN MORELOS
Smoke Detectors 9/13/2022 No Access for Inspection ALAN MORELOS
Verify Sprinkler Sign Off 9/13/2022 No Access for Inspection ALAN MORELOS
BUILDING-Rough-Frame 10/19/2022 Approved JACK KARGODORIAN
Final 10/19/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 10/19/2022 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV Approved JACK KARGODORIAN
Service/Power Release 10/19/2022 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 10/19/2022 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 10/19/2022 Approved JACK KARGODORIAN
Final 11/9/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 11/9/2022 Not Ready for Inspection JACK KARGODORIAN
Service/Power Release 11/9/2022 Approved JACK KARGODORIAN
Final 11/17/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 11/17/2022 Approved JACK KARGODORIAN