11834 W PACIFIC AVE 90066
Certificate Information: 11834 W PACIFIC AVE 90066
- Application / Permit
- 20010-20000-02663
- Plan Check / Job No.
- B20VN10250
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW RECREATION ROOM #2. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/14/2021
- Issuing Office
- Current Status
- CofO in Progress on 8/24/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | COLIN LOREDO |
| Corrections Issued | 8/31/2020 | COLIN LOREDO |
| Quality Review Completed | 9/24/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 9/25/2020 | APPLICANT |
| Plan Check Approved | 1/14/2021 | COLIN LOREDO |
| Issued | 1/14/2021 | APPLICANT |
| CofO in Progress | 8/24/2021 | ENRIQUE MIRELES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2020 | DINAH GARIN |
| Sewer availability | Cleared | 11/13/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 12/10/2020 | MARTIN FRAGOSO |
| Specific Plan | Cleared | 12/10/2020 | VALERIA CEJA |
| Construction within easement | Cleared | 12/31/2020 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 12/31/2020 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/8/2021 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 2/8/2021 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/17/2021 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/17/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/5/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 4/5/2021 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/5/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/8/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/8/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/8/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 4/8/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/8/2021 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 4/8/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 4/12/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/12/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/14/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/19/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/19/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 4/19/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/20/2021 | Approved | ENRIQUE MIRELES |
| Final | 7/27/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 7/27/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 7/27/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 7/27/2021 | Approved | ENRIQUE MIRELES |
| Final | 8/12/2021 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 8/12/2021 | Approved | ENRIQUE MIRELES |
| Final | 8/24/2021 | OK to Issue CofO | ENRIQUE MIRELES |