11834 W PACIFIC AVE 90066
Certificate Information: 11834 W PACIFIC AVE 90066
- Application / Permit
- 20010-20000-02661
- Plan Check / Job No.
- B20VN10250
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY, IRREGULAR SHAPED (71'-7" X 46'-11") SINGLE FAMILY DWELLING W/ ATTACHED GARAGE. NFPA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING. SUPPLEMENTAL PERMIT IS REQUIRED PRIOR TO CERTIFICATE OF OCCUPANCY TO RECORD AFFIDAVIT REGARDING THE PAYMENT OF FEES TO THE CITY OF LOS ANGELES (LINKAGE FEES).
- Permit Issued
- Issued on 1/14/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | COLIN LOREDO |
| Corrections Issued | 8/31/2020 | COLIN LOREDO |
| Quality Review Completed | 9/24/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 9/25/2020 | APPLICANT |
| Plan Check Approved | 1/7/2021 | COLIN LOREDO |
| Issued | 1/14/2021 | APPLICANT |
| CofO in Progress | 8/24/2021 | ENRIQUE MIRELES |
| Permit Finaled | 8/27/2021 | KENNETH NAGLE |
| CofO Issued | 8/27/2021 | KENNETH NAGLE |
| Permit Finaled | 8/27/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2020 | DINAH GARIN |
| Sewer availability | Cleared | 10/30/2020 | DINAH GARIN |
| Frnt yard landscape/Water mgmt | Cleared | 11/5/2020 | MIGUEL GAMBOA |
| Trees in Parkway | Cleared | 11/30/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 12/1/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/10/2020 | MARTIN FRAGOSO |
| Specific Plan | Cleared | 12/10/2020 | VALERIA CEJA |
| Construction within easement | Cleared | 12/31/2020 | RIDWAN HARDY |
| Permit | Cleared | 12/31/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 12/31/2020 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/8/2021 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 2/8/2021 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/17/2021 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/17/2021 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 2/18/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2021 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/5/2021 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Rough | 4/5/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/5/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/8/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/8/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/8/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 4/8/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/8/2021 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 4/8/2021 | Approved | ENRIQUE MIRELES |
| Wood Frame | 4/8/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 4/12/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/12/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/14/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/19/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/19/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 4/19/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/20/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/7/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Gas Test | 7/7/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 7/7/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 7/7/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/8/2021 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 7/8/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 7/8/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/8/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/27/2021 | Approved | ENRIQUE MIRELES |
| Final | 7/27/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 7/27/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 7/27/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 7/27/2021 | Approved | ENRIQUE MIRELES |
| Final | 8/12/2021 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 8/12/2021 | Approved | ENRIQUE MIRELES |
| Final | 8/24/2021 | OK to Issue CofO | ENRIQUE MIRELES |