15754 W ADDISON ST 91436
Certificate Information: 15754 W ADDISON ST 91436
- Application / Permit
- 20010-20000-02649
- Plan Check / Job No.
- B20VN10230
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- (N) 19'-3" X 12'-2" PATIO COVER ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/10/2020
- Issuing Office
- Current Status
- CofO Corrected on 9/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 9/3/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 9/21/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 9/22/2020 | APPLICANT |
| Applicant returned to address corrections | 11/24/2020 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 12/9/2020 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 12/10/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 12/10/2020 | APPLICANT |
| CofO in Progress | 9/10/2021 | RONALD COWAN |
| CofO Issued-Status Void | 9/27/2021 | MICHAEL SMITH |
| Permit Finaled-Status Void | 9/27/2021 | MICHAEL SMITH |
| Re-Activate Permit | 9/28/2021 | MICHAEL SMITH |
| CofO Corrected | 9/28/2021 | MICHAEL SMITH |
| Permit Finaled | 9/28/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 11/19/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/23/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/25/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | El Cabinet Corp; Lic. No.: 998351-B | 5657 WILKINSON AVE VALLEY VILLAGE, CA 91607 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/15/2020 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 12/24/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 3/2/2021 | Not Ready for Inspection | RONALD COWAN |
| HVAC-Rough | 3/2/2021 | Corrections Issued | RONALD COWAN |
| PLUMBING-Rough | 3/2/2021 | Not Ready for Inspection | RONALD COWAN |
| ELECTRICAL-Rough | 3/8/2021 | Approved | RONALD COWAN |
| HVAC-Rough | 3/8/2021 | Approved | RONALD COWAN |
| PLUMBING-Rough | 3/8/2021 | Approved | RONALD COWAN |
| Rough-Elec/Plmb/HVAC | 3/8/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 3/18/2021 | Partial Approval | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Not Ready | RONALD COWAN |
| BUILDING-Rough-Frame | 4/26/2021 | Not Ready for Inspection | RONALD COWAN |
| Drywall Nailing | 4/26/2021 | Approved | RONALD COWAN |
| Insulation | 4/26/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 4/26/2021 | Approved | RONALD COWAN |
| Verify Sprinkler Sign Off | 4/26/2021 | Not Ready for Inspection | RONALD COWAN |
| BUILDING-Rough-Frame | 8/19/2021 | Approved | MICHAEL PELHAM |
| Final | 8/19/2021 | Corrections Issued | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 8/19/2021 | SGSOV Not Ready | MICHAEL PELHAM |
| Service/Power Release | 8/19/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Smoke Detectors | 8/19/2021 | Approved | MICHAEL PELHAM |
| Verify Sprinkler Sign Off | 8/19/2021 | Approved | MICHAEL PELHAM |
| Final | 9/1/2021 | Corrections Issued | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2021 | SGSOV Approved | RONALD COWAN |
| Service/Power Release | 9/1/2021 | Approved | RONALD COWAN |
| Final | 9/10/2021 | OK to Issue CofO | RONALD COWAN |