17341 W AMINA PL 91316
Certificate Information: 17341 W AMINA PL 91316
- Application / Permit
- 20010-20000-02638
- Plan Check / Job No.
- B20VN10195
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- (N) 17' X 13' ONE STORY RECREATION ROOM, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/3/2021
- Issuing Office
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/3/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/3/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 9/3/2020 | APPLICANT |
| Applicant returned to address corrections | 6/15/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 7/8/2021 | RARES BODEA |
| Plan Check Approved | 8/3/2021 | RARES BODEA |
| Issued | 8/3/2021 | APPLICANT |
| CofO in Progress | 9/6/2024 | JON MCHUGH |
| CofO in Progress | 10/1/2024 | SEAN WIRCH |
| Permit Finaled | 10/15/2024 | JOHN JANSON |
| CofO Issued | 10/15/2024 | JOHN JANSON |
| Permit Finaled | 10/15/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2021 | JOHN TRIANTAFYLLOS |
| Miscellaneous | Cleared | 3/4/2021 | LAUREN PADICK |
| Miscellaneous | Cleared | 3/4/2021 | LAUREN PADICK |
| Tract Map conditions | Cleared | 3/4/2021 | LAUREN PADICK |
| Low Impact Development | Cleared | 6/8/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/12/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/7/2021 | Corrections Issued | STEVEN BACK |
| Deputy Reinf. Concrete | 9/8/2021 | Conditional Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 9/15/2021 | No Access for Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 9/22/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 9/22/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/4/2021 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Approved | STEVEN BACK |
| Green Building Rough | 10/4/2021 | Not Ready for Inspection | STEVEN BACK |
| Verify Sprinkler Sign Off | 10/4/2021 | Approved | STEVEN BACK |
| Deputy Wood Construction | 6/10/2022 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 7/19/2022 | Approved | JEFFREY BULL |
| Green Building Rough | 7/19/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 7/19/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 7/19/2022 | Not Ready for Inspection | JEFFREY BULL |
| Drywall Nailing | 8/18/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 9/26/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 9/28/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 9/28/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 10/16/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 4/17/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 4/17/2024 | Not Ready for Inspection | JON MCHUGH |
| Final | 4/17/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 4/17/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/17/2024 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 4/17/2024 | Not Required | JON MCHUGH |
| Smoke Detectors | 4/17/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 9/5/2024 | Approved | JON MCHUGH |
| Final | 9/5/2024 | OK to Issue CofO | JON MCHUGH |