812 N VISTA ST 90046

Certificate Information: 812 N VISTA ST 90046

Application / Permit
20010-20000-02636
Plan Check / Job No.
B20VN10194
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 89'-3" X 38' (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/7/2022
Issuing Office
Current Status
CofO Issued on 6/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 SELLA BENYAMIN
Corrections Issued 9/2/2020 SELLA BENYAMIN
Quality Review Completed 9/11/2020 STEVEN KIM
Building Plans Picked Up 9/29/2020 APPLICANT
Plan Check Approved 3/16/2021 SELLA BENYAMIN
Issued 2/7/2022 APPLICANT
CofO in Progress 6/16/2023 LILIANA PORTILLO
Permit Finaled 6/18/2023 DEROLD HAUFF
Permit Finaled 6/18/2023 DEROLD HAUFF
CofO Issued 6/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 10/22/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/26/2020 JEANIE LAM
Trees in Parkway Cleared 10/27/2020 JOHN KIM
Hydrant and Access approval Cleared 11/23/2020 MATTHEW CRAIG
Low Impact Development Cleared 12/1/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/8/2020 THOMAS LANG
Sewer availability Cleared 3/1/2021 WALLIE JONG

Contact Information

Contractor Aria Building Group Inc; Lic. No.: 1066127-B 18375 VENTURA BLVD #257      TARZANA, CA 91356
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/14/2022 Approved ARTHUR SARGSYAN
Deputy Reinf. Concrete 3/18/2022 Corrections Issued CRAIG DAVIS
Footing/Foundation/Slab 3/18/2022 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 3/21/2022 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 4/18/2022 Approved ALIZAH MAYAGOITIA
Special/Order Compliance 4/18/2022 Approved RUBEN SALAS
Deputy Reinf. Concrete 4/19/2022 Conditional Approval ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 4/22/2022 Conditional Approval ALIZAH MAYAGOITIA
Wood Frame 5/10/2022 Partial Approval ADAM ESCOTO
Wood Frame 5/17/2022 Partial Approval ADAM ESCOTO
BUILDING-Rough-Frame 6/29/2022 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 6/29/2022 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 6/29/2022 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 6/29/2022 Approved JOSEPH MCGARRY
PLUMBING-Rough 6/29/2022 Approved JOSEPH MCGARRY
Structural Steel Frame 6/29/2022 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 6/29/2022 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 6/29/2022 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 7/14/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/14/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 7/14/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 7/14/2022 Approved ALIZAH MAYAGOITIA
Structural Steel Frame 7/14/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 7/14/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/20/2022 Conditional Approval ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Approved ADAM ESCOTO
Green Building Rough 7/20/2022 Not Ready for Inspection ADAM ESCOTO
Structural Steel Frame 7/20/2022 Approved ADAM ESCOTO
Verify Sprinkler Sign Off 7/20/2022 Approved ADAM ESCOTO
Insulation 8/2/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/11/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 8/18/2022 Approved MICHAEL LEWIS
Drywall Nailing 8/23/2022 Approved MICHAEL LEWIS
Gas Test 8/23/2022 Approved MICHAEL LEWIS
ELECTRICAL-Final 3/31/2023 Approved MICHAEL LEWIS
PLUMBING-Final 3/31/2023 Approved MICHAEL LEWIS
Green Building Final 4/5/2023 Approved MICHAEL LEWIS
HVAC-Final 4/5/2023 Corrections Issued MICHAEL LEWIS
Service/Power Release 4/5/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/23/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/23/2023 Approved LILIANA PORTILLO
Final 5/23/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/23/2023 Approved LILIANA PORTILLO
Green Building Rough 5/23/2023 Approved LILIANA PORTILLO
HVAC-Final 5/23/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 5/23/2023 Approved LILIANA PORTILLO
Final 6/8/2023 Conditional Approval LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/8/2023 SGSOV Approved LILIANA PORTILLO
Final 6/14/2023 Conditional Approval LILIANA PORTILLO