11041 1/2 W HORTENSE ST 91602

Certificate Information: 11041 1/2 W HORTENSE ST 91602

Application / Permit
20010-20000-02620
Plan Check / Job No.
B20VN10107
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 40'-4" X 27' GARAGE, REC ROOM AND STORAGE (FOUNDATION TO REMAIN) AND ADD 27'-2" X 40'-6" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED GARAGE
Permit Issued
Issued on 12/10/2021
Issuing Office
Current Status
CofO Issued on 1/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 SELLA BENYAMIN
Corrections Issued 12/3/2020 SELLA BENYAMIN
Quality Review Completed 12/8/2020 STEVEN KIM
Building Plans Picked Up 12/14/2020 APPLICANT
Applicant returned to address corrections 11/2/2021 SELLA BENYAMIN
Plan Check Approved 12/3/2021 SELLA BENYAMIN
Issued 12/10/2021 APPLICANT
CofO in Progress 12/29/2022 JACK KARGODORIAN
CofO Issued 1/10/2023 MICHAEL SMITH
Permit Finaled 1/10/2023 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 9/12/2021 JORGE MEJIA LEMUS
Address approval Cleared 9/30/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/1/2021 CARLOS AGUILERA
Sewer availability Cleared 10/1/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 10/12/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/25/2021 GILBERT URREA

Contact Information

Contractor Dillon Construction Inc; Lic. No.: 1026965-B 1550 N MARINE AVENUE      WILMINGTON, CA 94744
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 12/15/2021 Corrections Issued THOMAS FINNILA
Wood Frame 12/20/2021 Corrections Issued THOMAS FINNILA
Wood Frame 12/29/2021 Not Ready for Inspection THOMAS FINNILA
Wood Frame 1/4/2022 Conditional Approval MATT KELLERMAN
BUILDING-Rough-Frame 1/18/2022 Not Ready for Inspection MICHAEL TEMPLE
ELECTRICAL-Rough 1/18/2022 Corrections Issued MICHAEL TEMPLE
Green Building Rough 1/18/2022 Not Ready for Inspection MICHAEL TEMPLE
MERV13>=Rough 1/18/2022 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Rough 1/18/2022 Not Ready for Inspection MICHAEL TEMPLE
Rough-Elec/Plmb/HVAC 1/18/2022 Not Ready for Inspection MICHAEL TEMPLE
ELECTRICAL-Rough 1/21/2022 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 1/21/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 1/25/2022 Approved CALEB MEISTER
HVAC-Rough 1/25/2022 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 1/25/2022 Not Ready for Inspection CALEB MEISTER
Underground Mechanical 1/25/2022 Conditional Approval CALEB MEISTER
Underground Mechanical 1/31/2022 Not Ready for Inspection THOMAS FINNILA
Wood Frame 1/31/2022 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 2/7/2022 Not Ready for Inspection DAVID MATSON
Green Building Rough 2/7/2022 Not Ready for Inspection DAVID MATSON
HVAC-Rough 2/7/2022 Not Ready for Inspection DAVID MATSON
MERV13>=Rough 2/7/2022 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 2/7/2022 Corrections Issued DAVID MATSON
BUILDING-Rough-Frame 2/9/2022 Partial Approval MATT KELLERMAN
PLUMBING-Rough 2/9/2022 Approved MATT KELLERMAN
Sewer 2/9/2022 Partial Approval MATT KELLERMAN
Wood Frame 2/16/2022 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 2/28/2022 No Access for Inspection THOMAS FINNILA
Green Building Rough 2/28/2022 No Access for Inspection THOMAS FINNILA
MERV13>=Rough 2/28/2022 No Access for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 3/7/2022 Approved MATT KELLERMAN
Green Building Rough 3/7/2022 Approved MATT KELLERMAN
MERV13>=Rough 3/7/2022 Approved MATT KELLERMAN
Insulation 3/15/2022 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 3/15/2022 Not Ready for Inspection CALEB MEISTER
Insulation 3/22/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 3/22/2022 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 4/7/2022 Approved MATT KELLERMAN
Drywall Nailing 4/21/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/31/2022 Approved WILLIAM WREN
Shower Pan 5/31/2022 Approved WILLIAM WREN
Gas Test 8/18/2022 Not Ready for Inspection THOMAS FINNILA
Sewer 8/18/2022 Approved THOMAS FINNILA
Gas Test 8/23/2022 Corrections Issued THOMAS FINNILA
HVAC-Final 8/23/2022 Corrections Issued THOMAS FINNILA
PLUMBING-Final 8/23/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 10/11/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 10/11/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 10/11/2022 Approved CHRISTOPHER DELLEFIELD
Gas Test 10/11/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Final 10/11/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 10/11/2022 Corrections Issued CHRISTOPHER DELLEFIELD
MERV13>=Final 10/11/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/11/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 10/11/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 10/11/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 10/28/2022 Approved JACK KARGODORIAN
Final 10/28/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 10/28/2022 Approved JACK KARGODORIAN
HVAC-Final 10/28/2022 Approved JACK KARGODORIAN
PLUMBING-Final 10/28/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Approved JACK KARGODORIAN
Service/Power Release 10/28/2022 Not Ready for Inspection JACK KARGODORIAN
Service/Power Release 11/3/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 12/29/2022 Approved JACK KARGODORIAN
Final 12/29/2022 OK to Issue CofO JACK KARGODORIAN