12834 W INDIANAPOLIS ST 90066

Certificate Information: 12834 W INDIANAPOLIS ST 90066

Application / Permit
20010-20000-02611
Plan Check / Job No.
B20VN10045
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT
Permit Issued
Issued on 6/9/2021
Issuing Office
Current Status
CofO Issued on 1/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 NILOOFAR MEHRAIN
Corrections Issued 8/25/2020 NILOOFAR MEHRAIN
Quality Review Completed 8/25/2020 CHON CHIO KUO
Building Plans Picked Up 8/26/2020 APPLICANT
Applicant returned to address corrections 5/7/2021 NILOOFAR MEHRAIN
Plan Check Approved 5/26/2021 NILOOFAR MEHRAIN
Issued 6/9/2021 APPLICANT
CofO in Progress 1/25/2023 RICHARD STEINBACH
Permit Finaled 1/26/2023 DANIEL ORRANTE
CofO Issued 1/26/2023 DANIEL ORRANTE
Permit Finaled 1/26/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/15/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/16/2020 DINAH GARIN
Sewer availability Cleared 9/16/2020 DINAH GARIN
GPI Written Notices Cleared 1/6/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 1/6/2021 NILOOFAR MEHRAIN
Construction near power lines Cleared 1/9/2021 RIDWAN HARDY
Construction within easement Cleared 1/9/2021 RIDWAN HARDY
Low Impact Development Cleared 3/10/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/16/2021 DINAH GARIN
Hydrant and Access approval Cleared 4/25/2021 MATTHEW CRAIG
Green Code Cleared 5/7/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/26/2021 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 8/30/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 8/30/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/16/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 Approved ENRIQUE MIRELES
Wood Frame 12/9/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Approved ENRIQUE MIRELES
Wood Frame 1/25/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 2/22/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/22/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/22/2022 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 3/4/2022 Approved ENRIQUE MIRELES
HVAC-Rough 3/4/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/10/2022 Corrections Issued JOHNNY MIRANDA
Wood Frame 3/10/2022 Not Ready for Inspection JOHNNY MIRANDA
Insulation 4/5/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Rough 4/5/2022 Corrections Issued PATRICK QUALEY
Wood Frame 4/5/2022 Corrections Issued PATRICK QUALEY
Special/Order Compliance 4/6/2022 Partial Inspection PATRICK QUALEY
BUILDING-Rough-Frame 4/8/2022 Conditional Approval PATRICK QUALEY
Green Building Rough 4/8/2022 Approved PATRICK QUALEY
Insulation 4/8/2022 Conditional Approval PATRICK QUALEY
PLUMBING-Rough 4/8/2022 Approved PATRICK QUALEY
Shower Pan 4/14/2022 Approved CLAYTON GRAHAM
Drywall Nailing 4/27/2022 Approved PATRICK QUALEY
PLUMBING-Rough 4/27/2022 Approved PATRICK QUALEY
Sewer 4/27/2022 Approved PATRICK QUALEY
BUILDING-Rough-Frame 10/24/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/24/2022 Corrections Issued JESUS RODRIGUEZ
Final 10/24/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 10/24/2022 Approved JESUS RODRIGUEZ
HVAC-Final 10/24/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 10/24/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Not Ready JESUS RODRIGUEZ
Service/Power Release 10/24/2022 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 10/24/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 1/12/2023 Approved JESUS RODRIGUEZ
Final 1/12/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 1/12/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/12/2023 SGSOV Not Ready JESUS RODRIGUEZ
Service/Power Release 1/12/2023 Approved JESUS RODRIGUEZ
Final 1/24/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Final 1/24/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/24/2023 SGSOV Approved JESUS RODRIGUEZ