20124 W PICCADILLY LANE 91326

Certificate Information: 20124 W PICCADILLY LANE 91326

Application / Permit
20010-20000-02596
Plan Check / Job No.
B20VN09998
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
(N) OPEN TRELLIS PATIO (17' X 17') PER ENG'R DESIGN
Permit Issued
Issued on 10/12/2020
Issuing Office
Current Status
CofO Issued on 9/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2020 APPLICANT
Assigned to Plan Check Engineer 8/14/2020 NILOOFAR MEHRAIN
Corrections Issued 8/18/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 8/18/2020 APPLICANT
Plan Check Approved 9/22/2020 NILOOFAR MEHRAIN
Issued 10/12/2020 APPLICANT
CofO in Progress 8/2/2025 MICHAEL PELHAM
Permit Finaled 9/5/2025 MICHAEL PELHAM
CofO Issued 9/5/2025 MICHAEL PELHAM
Permit Finaled 9/5/2025 MICHAEL PELHAM

Permit Application Clearance Information

"T" removal Cleared 8/26/2020 NOAH MCCOY
Miscellaneous Cleared 8/26/2020 NOAH MCCOY
Miscellaneous Cleared 8/26/2020 NOAH MCCOY
Miscellaneous Cleared 8/26/2020 NOAH MCCOY
Specific Plan Cleared 8/26/2020 NOAH MCCOY
Tract Map conditions Cleared 8/26/2020 NOAH MCCOY
ZA Case Cleared 8/26/2020 NOAH MCCOY
ZA Case Cleared 8/26/2020 NOAH MCCOY
ZI Cleared 8/26/2020 NOAH MCCOY
Grading Pre-Inspection Cleared 9/22/2020 NILOOFAR MEHRAIN

Contact Information

Contractor Miller Steven Louis; Lic. No.: 474691-B 15021 VENTURA BLVD 702      SHERMAN OAKS, CA 91403
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/19/2020 Approved DAVID SCANTLIN
Footing/Foundation/Slab 10/19/2020 Approved DAVID SCANTLIN
Reinforced Concrete Frame 10/29/2020 Approved DAVID SCANTLIN
Reinforced Masonry Frame 10/29/2020 Approved DAVID SCANTLIN
Final 7/23/2021 Corrections Issued DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 7/23/2021 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 7/23/2021 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 7/23/2021 Approved DAVID SCANTLIN
Wood Frame 7/23/2021 Approved DAVID SCANTLIN
Final 8/2/2025 OK to Issue CofO MICHAEL PELHAM