10407 N HADDON AVE 91331

Certificate Information: 10407 N HADDON AVE 91331

Application / Permit
20010-20000-02577
Plan Check / Job No.
B20VN09947
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 20' X 20' TWO CAR GARAGE.
Permit Issued
Issued on 7/21/2021
Issuing Office
Current Status
CofO Issued on 10/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2020 APPLICANT
Assigned to Plan Check Engineer 8/11/2020 SERGIO MUNIZ
Corrections Issued 8/12/2020 SERGIO MUNIZ
Applicant returned to address corrections 3/15/2021 SERGIO MUNIZ
Applicant returned to address corrections 5/12/2021 SERGIO MUNIZ
Applicant returned to address corrections 6/7/2021 SERGIO MUNIZ
Applicant returned to address corrections 6/22/2021 SERGIO MUNIZ
Applicant returned to address corrections 7/6/2021 SERGIO MUNIZ
Plan Check Approved 7/21/2021 SERGIO MUNIZ
Issued 7/21/2021 APPLICANT
Building Plans Picked Up 8/4/2021 APPLICANT
CofO in Progress 10/20/2025 MICHEL ABAJAN
Permit Finaled 10/24/2025 RUBEN SALAS
CofO Issued 10/24/2025 RUBEN SALAS
Permit Finaled 10/24/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/8/2020 ADRIAN CASTRO
Clean Up Green Up Cleared 11/24/2020 PABLO ESTRADA
Low Impact Development Cleared 2/21/2021 ORVAL HERNANDEZ-MARCI
Construction near power lines Cleared 2/27/2021 TORI CHEN
Roof/Waste drainage to street Cleared 6/15/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Hajdari,, Gentjan; Lic. No.: C88031 157 S LOS ROBLES AVE 12      PASADENA, CA 91101

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/22/2022 Corrections Issued MICHEL ABAJAN
METHANE-Barrier 9/22/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 9/22/2022 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 10/3/2022 Conditional Approval MICHEL ABAJAN
Wood Frame 12/28/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/10/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 2/10/2023 Approved MICHEL ABAJAN
Insulation 8/7/2023 Approved MICHEL ABAJAN
Drywall Nailing 8/15/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 4/24/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/24/2025 Approved MICHEL ABAJAN
Final 4/24/2025 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 4/24/2025 Approved MICHEL ABAJAN
Green Building Final 4/24/2025 Approved MICHEL ABAJAN
Green Building Rough 4/24/2025 Approved MICHEL ABAJAN
METHANE-Final 4/24/2025 Approved MICHEL ABAJAN
METHANE-Rough 4/24/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 4/24/2025 Approved MICHEL ABAJAN
Final 10/17/2025 OK to Issue CofO MICHEL ABAJAN