13525 W ROMANY DR 90272
Certificate Information: 13525 W ROMANY DR 90272
- Application / Permit
- 20010-20000-02568
- Plan Check / Job No.
- B20VN09931
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE TWO STORY SFD WITH 3-CAR GARAGE AND HABITABLE BASEMENT_BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 11/19/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | DAWN MC NULTY |
| Corrections Issued | 8/31/2020 | DAWN MC NULTY |
| Quality Review Completed | 8/31/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 9/2/2020 | APPLICANT |
| Applicant returned to address corrections | 10/5/2020 | DAWN MC NULTY |
| Applicant returned to address corrections | 10/7/2020 | DAWN MC NULTY |
| Applicant returned to address corrections | 11/9/2020 | DAWN MC NULTY |
| Plan Check Approved | 11/16/2020 | DAWN MC NULTY |
| Issued | 11/19/2020 | APPLICANT |
| CofO in Progress | 11/17/2022 | JUAN VALENZUELA |
| Permit Finaled | 12/13/2022 | DANIEL ORRANTE |
| CofO Issued | 12/13/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/13/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2020 | NIKTA MOUSAVI |
| Trees in Parkway | Cleared | 9/14/2020 | JOHN KIM |
| Work Adjacent to Public Way | Cleared | 9/14/2020 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2020 | NIKTA MOUSAVI |
| Permit | Cleared | 9/22/2020 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 9/22/2020 | NIKTA MOUSAVI |
| Frnt yard landscape/Water mgmt | Cleared | 9/30/2020 | MIGUEL GAMBOA |
| GPI Written Notices | Cleared | 10/7/2020 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 10/7/2020 | DAWN MC NULTY |
| Miscellaneous | Cleared | 10/7/2020 | DAWN MC NULTY |
| Hydrant and Access approval | Cleared | 10/8/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/21/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/23/2020 | NIKTA MOUSAVI |
| Excavation more than 5-ft deep | Cleared | 11/16/2020 | CALOSHA APPROVED |
Contact Information
| Architect | Ungar,, Kenneth Joel; Lic. No.: C21777 | 1173 WESTBEND ROAD WESTLAKE VILLAGE, CA 91362 |
| Contractor | T Apple General Contracting Incorporated; Lic. No.: 1064015-B | 760 N TOWNE AVE CLAREMONT, CA 91711 |
| Engineer | Danz,, Joshua Franklin; Lic. No.: C84764 | 1164 ELDERBERRY CIRCLE FOLSOM, CA 95630 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Tani,, Jason Yukio; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/13/2021 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 1/15/2021 | Not Ready for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 1/28/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 1/28/2021 | Partial Approval | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 2/1/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 2/2/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 2/16/2021 | Conditional Approval | CARLOS MATAMOROS |
| Green Building Rough | 2/16/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Reinforced Concrete Frame | 2/16/2021 | Partial Approval | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 2/16/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Reinf. Concrete | 2/17/2021 | Approved | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/21/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/6/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 5/6/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Structural Steel Frame | 5/6/2021 | Partial Approval | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 5/6/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 7/19/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 7/19/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 7/19/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Wood Frame | 7/19/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2021 | Not Ready for Inspection | MORRIS JACKSON |
| Wood Frame | 7/21/2021 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 7/23/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 7/23/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/28/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2021 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 9/28/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 9/28/2021 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 10/18/2021 | Corrections Issued | JUAN VALENZUELA |
| Gas Test | 10/18/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 10/18/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 10/18/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Gas Test | 10/21/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 10/21/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Pre-Inspection | 10/21/2021 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 10/27/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 11/1/2021 | Partial Approval | ANDREW NAVE |
| Wood Frame | 11/1/2021 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 11/4/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 11/4/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 11/5/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 11/5/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 11/5/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 11/5/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 11/5/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 11/9/2021 | Partial Approval | JOHN KIDWELL |
| Insulation | 11/10/2021 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 11/17/2021 | Partial Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 11/17/2021 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 11/24/2021 | Partial Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 12/10/2021 | Partial Approval | DEANDRE HOFFMAN |
| PLUMBING-Rough | 12/15/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/17/2021 | Partial Approval | ANDREW NAVE |
| HVAC-Rough | 12/17/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 12/21/2021 | Partial Approval | JUAN VALENZUELA |
| Insulation | 12/21/2021 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 1/6/2022 | Approved | JOHN KIDWELL |
| Underground Mechanical | 3/9/2022 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 3/16/2022 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 4/6/2022 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 4/7/2022 | Partial Approval | JUAN VALENZUELA |
| Gas Test | 9/8/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 9/8/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 9/22/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 9/27/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 9/27/2022 | Approved | JUAN VALENZUELA |
| Service/Power Release | 9/29/2022 | Approved | JUAN VALENZUELA |
| HVAC-Final | 10/7/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/10/2022 | Corrections Issued | JUAN VALENZUELA |
| Final | 11/10/2022 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 11/10/2022 | Approved | JUAN VALENZUELA |
| Reinforced Concrete Frame | 11/10/2022 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 11/10/2022 | Approved | JUAN VALENZUELA |
| Structural Steel Frame | 11/10/2022 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/16/2022 | Approved | JUAN VALENZUELA |
| Final | 11/16/2022 | OK to Issue CofO | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | JUAN VALENZUELA |
| Structural Steel Frame | 11/16/2022 | Approved | JUAN VALENZUELA |