13525 W ROMANY DR 90272

Certificate Information: 13525 W ROMANY DR 90272

Application / Permit
20010-20000-02568
Plan Check / Job No.
B20VN09931
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY SFD WITH 3-CAR GARAGE AND HABITABLE BASEMENT_BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 11/19/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 DAWN MC NULTY
Corrections Issued 8/31/2020 DAWN MC NULTY
Quality Review Completed 8/31/2020 CHON CHIO KUO
Building Plans Picked Up 9/2/2020 APPLICANT
Applicant returned to address corrections 10/5/2020 DAWN MC NULTY
Applicant returned to address corrections 10/7/2020 DAWN MC NULTY
Applicant returned to address corrections 11/9/2020 DAWN MC NULTY
Plan Check Approved 11/16/2020 DAWN MC NULTY
Issued 11/19/2020 APPLICANT
CofO in Progress 11/17/2022 JUAN VALENZUELA
Permit Finaled 12/13/2022 DANIEL ORRANTE
CofO Issued 12/13/2022 DANIEL ORRANTE
Permit Finaled 12/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/14/2020 NIKTA MOUSAVI
Trees in Parkway Cleared 9/14/2020 JOHN KIM
Work Adjacent to Public Way Cleared 9/14/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 9/15/2020 NIKTA MOUSAVI
Permit Cleared 9/22/2020 NIKTA MOUSAVI
Sewer availability Cleared 9/22/2020 NIKTA MOUSAVI
Frnt yard landscape/Water mgmt Cleared 9/30/2020 MIGUEL GAMBOA
GPI Written Notices Cleared 10/7/2020 DAWN MC NULTY
Grading Pre-Inspection Cleared 10/7/2020 DAWN MC NULTY
Miscellaneous Cleared 10/7/2020 DAWN MC NULTY
Hydrant and Access approval Cleared 10/8/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/21/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/23/2020 NIKTA MOUSAVI
Excavation more than 5-ft deep Cleared 11/16/2020 CALOSHA APPROVED

Contact Information

Architect Ungar,, Kenneth Joel; Lic. No.: C21777 1173 WESTBEND ROAD      WESTLAKE VILLAGE, CA 91362
Contractor T Apple General Contracting Incorporated; Lic. No.: 1064015-B 760 N TOWNE AVE      CLAREMONT, CA 91711
Engineer Danz,, Joshua Franklin; Lic. No.: C84764 1164 ELDERBERRY CIRCLE      FOLSOM, CA 95630
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Tani,, Jason Yukio; Lic. No.: C58271 5296 VIA PATRICIA      THOUSAND OAKS, CA 91320

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/13/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 1/15/2021 Not Ready for Inspection KENNETH NAGLE
ELECTRICAL-Rough 1/28/2021 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 1/28/2021 Partial Approval ANTHONY MCDOWALL
ELECTRICAL-Rough 2/1/2021 Not Ready for Inspection CARLOS MATAMOROS
Deputy Reinf. Concrete 2/2/2021 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 2/16/2021 Conditional Approval CARLOS MATAMOROS
Green Building Rough 2/16/2021 Not Ready for Inspection JOHN KIDWELL
Reinforced Concrete Frame 2/16/2021 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 2/16/2021 Not Ready for Inspection JOHN KIDWELL
Deputy Reinf. Concrete 2/17/2021 Approved ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 4/7/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/21/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/6/2021 Approved JUAN VALENZUELA
Green Building Rough 5/6/2021 Not Ready for Inspection JUAN VALENZUELA
Structural Steel Frame 5/6/2021 Partial Approval JUAN VALENZUELA
Verify Sprinkler Sign Off 5/6/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 7/19/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 Corrections Issued JUAN VALENZUELA
Green Building Rough 7/19/2021 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 7/19/2021 Not Ready for Inspection JUAN VALENZUELA
Wood Frame 7/19/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/21/2021 Not Ready for Inspection MORRIS JACKSON
Wood Frame 7/21/2021 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 7/23/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 7/23/2021 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 7/23/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 9/28/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/28/2021 Partial Approval JOHN KIDWELL
Green Building Rough 9/28/2021 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 9/28/2021 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 10/18/2021 Corrections Issued JUAN VALENZUELA
Gas Test 10/18/2021 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 10/18/2021 Approved JUAN VALENZUELA
PLUMBING-Rough 10/18/2021 Not Ready for Inspection JUAN VALENZUELA
Gas Test 10/21/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 10/21/2021 Not Ready for Inspection JUAN VALENZUELA
Pre-Inspection 10/21/2021 Partial Inspection JUAN VALENZUELA
PLUMBING-Rough 10/27/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 11/1/2021 Partial Approval ANDREW NAVE
Wood Frame 11/1/2021 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Rough 11/4/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 11/4/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 11/5/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 11/5/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 11/5/2021 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 11/5/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 11/5/2021 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 11/9/2021 Partial Approval JOHN KIDWELL
Insulation 11/10/2021 Not Ready for Inspection RYAN SALAZAR
Insulation 11/17/2021 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 11/17/2021 Partial Approval JUAN VALENZUELA
Drywall Nailing 11/24/2021 Partial Approval KRISTEN CAUSEY
Interior/Exterior Lathing 12/10/2021 Partial Approval DEANDRE HOFFMAN
PLUMBING-Rough 12/15/2021 Approved JUAN VALENZUELA
ELECTRICAL-Rough 12/17/2021 Partial Approval ANDREW NAVE
HVAC-Rough 12/17/2021 Approved ANDREW NAVE
BUILDING-Rough-Frame 12/21/2021 Partial Approval JUAN VALENZUELA
Insulation 12/21/2021 Partial Approval JUAN VALENZUELA
Drywall Nailing 1/6/2022 Approved JOHN KIDWELL
Underground Mechanical 3/9/2022 Partial Approval JUAN VALENZUELA
Underground Mechanical 3/16/2022 Partial Approval JUAN VALENZUELA
Underground Mechanical 4/6/2022 Partial Approval JOHN KIDWELL
Underground Mechanical 4/7/2022 Partial Approval JUAN VALENZUELA
Gas Test 9/8/2022 Approved JUAN VALENZUELA
PLUMBING-Final 9/8/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 9/22/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 9/27/2022 Approved JUAN VALENZUELA
PLUMBING-Final 9/27/2022 Approved JUAN VALENZUELA
Service/Power Release 9/29/2022 Approved JUAN VALENZUELA
HVAC-Final 10/7/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 11/10/2022 Corrections Issued JUAN VALENZUELA
Final 11/10/2022 Corrections Issued JUAN VALENZUELA
Green Building Final 11/10/2022 Approved JUAN VALENZUELA
Reinforced Concrete Frame 11/10/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/10/2022 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 11/10/2022 Approved JUAN VALENZUELA
Structural Steel Frame 11/10/2022 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 11/16/2022 Approved JUAN VALENZUELA
Final 11/16/2022 OK to Issue CofO JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Approved JUAN VALENZUELA
Structural Steel Frame 11/16/2022 Approved JUAN VALENZUELA