129-129 1/2 E 88TH ST 90003

Certificate Information: 129-129 1/2 E 88TH ST 90003

Application / Permit
20010-20000-02556
Plan Check / Job No.
B20VN09900
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW (41'-6"x 28'-0") 3-STORY DUPLEX WITH 4-CAR GARAGE, NFPA-13D FIRE SRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 3/17/2022
Issuing Office
Current Status
Issued on 3/17/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/3/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 TROY DEGUZMAN
Corrections Issued 8/26/2020 TROY DEGUZMAN
Quality Review Completed 8/26/2020 CHON CHIO KUO
Building Plans Picked Up 8/27/2020 APPLICANT
Applicant returned to address corrections 2/10/2022 TROY DEGUZMAN
Plan Check Approved 3/1/2022 TROY DEGUZMAN
Issued 3/17/2022 APPLICANT

Permit Application Clearance Information

Highway dedication Cleared 9/4/2020 JEANIE LAM
Address approval Cleared 9/15/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/15/2020 JEANIE LAM
Sewer availability Cleared 9/15/2020 JEANIE LAM
Low Impact Development Cleared 6/11/2021 MITESH PATEL
Specific Plan Cleared 8/6/2021 MAXFIELD VERMY
ZI Cleared 8/6/2021 MAXFIELD VERMY
Roof/Waste drainage to street Cleared 8/9/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 9/16/2021 ROBERT DUFF
Frnt yard landscape/Water mgmt Cleared 12/10/2021 MAXFIELD VERMY
Green Code Cleared 2/10/2022 TROY DEGUZMAN
Hold Cleared 4/5/2022 JASON SHEETS
Hold Cleared 4/5/2022 JASON SHEETS

Contact Information

Contractor Good News Construction Inc; Lic. No.: 967654-B 1434 WESTWOOD BLVD, STE $16      LOS ANGELES, CA 90024
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 6/9/2026   
Footing/Foundation/Slab 6/9/2026   
Green Building Final 6/9/2026   
Service/Power Release 6/9/2026   
BUILDING-Rough-Frame 6/9/2026   

Inspection Request History

Pre-Inspection 4/11/2022 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 4/27/2022 Partial Approval HORACE FULTZ
Sewer 4/27/2022 Partial Approval HORACE FULTZ
Excavation/Setback/Form/Re-Bar 5/6/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/6/2022 Corrections Issued LILIANA PORTILLO
Deputy Reinf. Concrete 5/10/2022 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 5/13/2022 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Partial Approval LILIANA PORTILLO
HVAC-Rough 11/10/2022 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 11/14/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 11/14/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 11/15/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 11/16/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 11/17/2022 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 11/17/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Approved LILIANA PORTILLO
Insulation 11/21/2022 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 11/22/2022 Conditional Approval LILIANA PORTILLO
Insulation 11/22/2022 Approved LILIANA PORTILLO
Shower Pan 12/6/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/7/2022 Conditional Approval LILIANA PORTILLO
Drywall Nailing 12/7/2022 Approved LILIANA PORTILLO
Green Building Rough 12/7/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 12/7/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/22/2022 Approved LILIANA PORTILLO
Underground Mechanical 4/26/2023 Not Ready for Inspection LILIANA PORTILLO
Underground Mechanical 5/2/2023 Approved MICHAEL LEWIS
Underground Mechanical 5/12/2023 Approved MICHAEL LEWIS
PLUMBING-Final 3/5/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 4/30/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Final 8/19/2025 Partial Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 3/5/2026 Partial Inspection JOHN QUINTANILLA
Smoke Detectors 3/5/2026 Approved JOHN QUINTANILLA