131-131 1/2 E 88TH ST 90003

Certificate Information: 131-131 1/2 E 88TH ST 90003

Application / Permit
20010-20000-02554
Plan Check / Job No.
B20VN09900
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW (41'-6"x 28'-0") 3-STORY DUPLEX WITH ATT. 4-CAR GARAGE, NFPA-13D FIRE SRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
Issued on 4/25/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/3/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 TROY DEGUZMAN
Corrections Issued 8/26/2020 TROY DEGUZMAN
Quality Review Completed 8/26/2020 CHON CHIO KUO
Building Plans Picked Up 8/27/2020 APPLICANT
Applicant returned to address corrections 2/10/2022 TROY DEGUZMAN
Plan Check Approved 3/1/2022 TROY DEGUZMAN
Issued 4/25/2022 APPLICANT

Permit Application Clearance Information

Highway dedication Cleared 9/4/2020 JEANIE LAM
Address approval Cleared 9/15/2020 JEANIE LAM
Sewer availability Cleared 9/15/2020 JEANIE LAM
Low Impact Development Cleared 6/11/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 8/9/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 9/16/2021 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 9/24/2021 PAMELA TENEZA
Specific Plan Cleared 11/22/2021 MAXFIELD VERMY
ZI Cleared 11/22/2021 MAXFIELD VERMY
Frnt yard landscape/Water mgmt Cleared 12/10/2021 MAXFIELD VERMY
Green Code Cleared 2/10/2022 TROY DEGUZMAN
Hold Cleared 4/28/2022 JASON SHEETS

Contact Information

Contractor Good News Construction Inc; Lic. No.: 967654-B 1434 WESTWOOD BLVD, STE $16      LOS ANGELES, CA 90024
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 6/9/2026   
Green Building Final 6/9/2026   
Service/Power Release 6/9/2026   
Drywall Nailing 6/9/2026   

Inspection Request History

PLUMBING-Rough 6/29/2022 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 7/5/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 7/5/2022 Conditional Approval LILIANA PORTILLO
Underground Mechanical 7/5/2022 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 7/7/2022 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 8/4/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/17/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 1/23/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/6/2023 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 2/6/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 2/21/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/21/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Conditional Approval LILIANA PORTILLO
Green Building Rough 2/21/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 2/21/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 2/21/2023 Approved LILIANA PORTILLO
HVAC-Rough 3/7/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Insulation 3/7/2023 Corrections Issued ALIZAH MAYAGOITIA
Wood Frame 3/7/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/10/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/10/2023 Approved LILIANA PORTILLO
Green Building Rough 3/10/2023 Approved LILIANA PORTILLO
HVAC-Rough 3/10/2023 Approved LILIANA PORTILLO
Insulation 3/10/2023 Approved LILIANA PORTILLO
Drywall Nailing 3/15/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 3/15/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/15/2023 Partial Approval LILIANA PORTILLO
Drywall Nailing 3/20/2023 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 3/20/2023 Approved LILIANA PORTILLO
Shower Pan 3/20/2023 Approved LILIANA PORTILLO
Underground Mechanical 5/2/2023 Approved MICHAEL LEWIS
Underground Mechanical 5/12/2023 Approved MICHAEL LEWIS
Underground Mechanical 5/17/2023 Approved MICHAEL LEWIS
PLUMBING-Final 2/27/2024 Not Ready for Inspection MICHAEL LEWIS
Gas Test 3/1/2024 Approved MICHAEL LEWIS
PLUMBING-Final 3/1/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 4/2/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 4/11/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 8/19/2025 Partial Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 3/5/2026 Partial Inspection JOHN QUINTANILLA
Smoke Detectors 3/5/2026 Approved JOHN QUINTANILLA