133-133 1/2 E 88TH ST 90003
Certificate Information: 133-133 1/2 E 88TH ST 90003
- Application / Permit
- 20010-20000-02553
- Plan Check / Job No.
- B20VN09900
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW (41'-6"x 28'-0") 3-STORY DUPLEX WITH ATT. REC ROOM AND 3-CAR GARAGE, NFPA-13D FIRE SRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- Issued on 4/25/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | TROY DEGUZMAN |
| Corrections Issued | 8/26/2020 | TROY DEGUZMAN |
| Quality Review Completed | 8/26/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 8/27/2020 | APPLICANT |
| Applicant returned to address corrections | 2/10/2022 | TROY DEGUZMAN |
| Plan Check Approved | 3/1/2022 | TROY DEGUZMAN |
| Issued | 4/25/2022 | APPLICANT |
Permit Application Clearance Information
| Highway dedication | Cleared | 9/4/2020 | JEANIE LAM |
| Permit | Cleared | 9/4/2020 | JEANIE LAM |
| Address approval | Cleared | 9/15/2020 | JEANIE LAM |
| Sewer availability | Cleared | 9/15/2020 | JEANIE LAM |
| Trees in Parkway | Cleared | 9/17/2020 | JOHN KIM |
| Low Impact Development | Cleared | 6/11/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/9/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 9/16/2021 | ROBERT DUFF |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2021 | PAMELA TENEZA |
| Specific Plan | Cleared | 11/22/2021 | MAXFIELD VERMY |
| ZI | Cleared | 11/22/2021 | MAXFIELD VERMY |
| Frnt yard landscape/Water mgmt | Cleared | 12/10/2021 | MAXFIELD VERMY |
| Green Code | Cleared | 2/10/2022 | TROY DEGUZMAN |
| Hold | Cleared | 4/28/2022 | JASON SHEETS |
Contact Information
| Contractor | Good News Construction Inc; Lic. No.: 967654-B | 1434 WESTWOOD BLVD, STE $16 LOS ANGELES, CA 90024 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2022 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/4/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Partial Approval | LILIANA PORTILLO |
| Wood Frame | 11/7/2022 | Corrections Issued | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 12/7/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 12/14/2022 | Approved | LILIANA PORTILLO |
| Deputy Wood Construction | 12/15/2022 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/19/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 12/22/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 12/22/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/27/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/30/2022 | Approved | LILIANA PORTILLO |
| Insulation | 12/30/2022 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/30/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Shower Pan | 12/30/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/5/2023 | Approved | LILIANA PORTILLO |
| Insulation | 1/5/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/5/2023 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/13/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 5/2/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 5/12/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 2/27/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Gas Test | 3/1/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 3/1/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 4/2/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Final | 4/11/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 8/19/2025 | Partial Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 3/5/2026 | SGSOV Approved | JOHN QUINTANILLA |
| Service/Power Release | 3/5/2026 | Partial Inspection | JOHN QUINTANILLA |
| Smoke Detectors | 3/5/2026 | Approved | JOHN QUINTANILLA |
| Final | 6/4/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 6/4/2026 | Partial Approval | JOHN QUINTANILLA |
| Service/Power Release | 6/4/2026 | Approved | JOHN QUINTANILLA |