9102 N LANIGAN AVE 91352
Certificate Information: 9102 N LANIGAN AVE 91352
- Application / Permit
- 20010-20000-02549
- Plan Check / Job No.
- B20VN09862
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28' X 45' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/5/2021
- Issuing Office
- Current Status
- Issued on 2/5/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/3/2020 | SELLA BENYAMIN |
| Quality Review Completed | 9/3/2020 | STEVEN KIM |
| Building Plans Picked Up | 9/3/2020 | APPLICANT |
| Plan Check Approved | 2/4/2021 | SELLA BENYAMIN |
| Issued | 2/5/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 8/31/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2020 | GABRIEL ROBLES |
| Private street | Cleared | 9/15/2020 | MIGUEL GAMBOA |
| Street Frontage | Cleared | 9/16/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/17/2020 | GABRIEL ROBLES |
| Specific Plan | Cleared | 11/4/2020 | PEGGY MALONE-BROWN |
| Low Impact Development | Cleared | 12/9/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/17/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 1/26/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 10/4/2023 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 10/17/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Not Ready for Inspection | DAVID ANDERSON |