7722 N WHITSETT AVE 91605
Certificate Information: 7722 N WHITSETT AVE 91605
- Application / Permit
- 20010-20000-02548
- Plan Check / Job No.
- B20VN09858
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20' X 37'-8"1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B).
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2020 | SERGIO MUNIZ |
| Corrections Issued | 8/10/2020 | SERGIO MUNIZ |
| Plan Check Approved | 3/15/2021 | SERGIO MUNIZ |
| Issued | 3/19/2021 | APPLICANT |
| Building Plans Picked Up | 3/25/2021 | APPLICANT |
| CofO in Progress | 12/7/2022 | MATTHEW NELSON |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/17/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 10/13/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 2/13/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/23/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/1/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/9/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| METHANE-Barrier | 7/9/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| METHANE-Subgrade | 7/9/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/22/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/22/2021 | Approved | GREGG CUMMINGS |
| METHANE-Barrier | 7/22/2021 | Approved | GREGG CUMMINGS |
| METHANE-Subgrade | 7/22/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/14/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 9/14/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 11/4/2021 | Approved | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 11/4/2021 | Approved | CHRISTOPHER DELLEFIELD |
| METHANE-Rough | 11/4/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 11/4/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 1/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 2/2/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 2/4/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2022 | Approved | WILLIAM WREN |
| Insulation | 2/18/2022 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 2/18/2022 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 3/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 3/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 3/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 3/4/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/4/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 3/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 3/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 8/4/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 10/17/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 10/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 10/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 10/17/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 10/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 10/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 10/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 10/17/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 10/17/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 10/17/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 11/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 11/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 11/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 11/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 11/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 11/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 11/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 11/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 11/29/2022 | Partial Approval | MATTHEW NELSON |
| Final | 11/29/2022 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Final | 11/29/2022 | Partial Approval | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 11/29/2022 | Corrections Issued | MATTHEW NELSON |
| Drywall Nailing | 12/6/2022 | Approved | MATTHEW NELSON |
| Final | 12/6/2022 | OK to Issue CofO | MATTHEW NELSON |
| MERV13>=Final | 12/6/2022 | Approved | MATTHEW NELSON |
| Service/Power Release | 12/6/2022 | Approved | MATTHEW NELSON |