8401 N HAZELTINE AVE 91402
Certificate Information: 8401 N HAZELTINE AVE 91402
- Application / Permit
- 20010-20000-02547
- Plan Check / Job No.
- B20VN09845
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- PROPOSED 20' X 20' DETACHED REC ROOM. ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/30/2020
- Issuing Office
- Current Status
- CofO Issued on 6/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2020 | RAPHAEL ROSAS |
| Corrections Issued | 8/13/2020 | RAPHAEL ROSAS |
| Issued | 9/30/2020 | APPLICANT |
| CofO in Progress | 2/8/2021 | GREGG CUMMINGS |
| CofO Issued | 6/26/2021 | MICHAEL SMITH |
| Permit Finaled | 6/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/18/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 9/30/2020 | OSCAR CASTRO |
| Construction within easement | Cleared | 9/30/2020 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/6/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 11/6/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 11/12/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/12/2020 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/4/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 12/4/2020 | Approved | GREGG CUMMINGS |
| Wood Frame | 12/4/2020 | Partial Approval | GREGG CUMMINGS |
| Insulation | 12/10/2020 | Approved | GREGG CUMMINGS |
| Wood Frame | 12/10/2020 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 12/15/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/15/2020 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/2/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/2/2021 | Corrections Issued | GREGG CUMMINGS |
| Final | 2/2/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/2/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 2/2/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/2/2021 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/2/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 2/2/2021 | Partial Inspection | GREGG CUMMINGS |
| Smoke Detectors | 2/2/2021 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 2/2/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/8/2021 | Approved | GREGG CUMMINGS |
| Final | 2/8/2021 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 2/8/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/8/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 2/8/2021 | Approved | GREGG CUMMINGS |