530 N BEACHWOOD DR 90004
Certificate Information: 530 N BEACHWOOD DR 90004
- Application / Permit
- 20010-20000-02520
- Plan Check / Job No.
- B20VN09756
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 16'-6" X 22'-6" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Current Status
- CofO Issued on 5/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | SELLA BENYAMIN |
| Corrections Issued | 12/10/2020 | SELLA BENYAMIN |
| Quality Review Completed | 12/16/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/16/2020 | APPLICANT |
| Plan Check Approved | 6/8/2021 | SELLA BENYAMIN |
| Issued | 6/22/2021 | APPLICANT |
| CofO in Progress | 4/28/2022 | SHAVONNE ESPINOZA |
| Permit Finaled | 5/16/2022 | DEROLD HAUFF |
| CofO Issued | 5/16/2022 | DEROLD HAUFF |
| Permit Finaled | 5/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/4/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 4/13/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 5/20/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/27/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/1/2021 | JEANIE LAM |
Contact Information
| Contractor | Refined Home Construction Inc; Lic. No.: 1001310-B | 113 N SAN VICENTE BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/15/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/15/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/15/2021 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 10/15/2021 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 10/19/2021 | Not Ready for Inspection | MASHEL JONGERT |
| Interior/Exterior Lathing | 10/22/2021 | Partial Approval | MASHEL JONGERT |
| Shower Pan | 10/22/2021 | Approved | MASHEL JONGERT |
| Interior/Exterior Lathing | 11/1/2021 | Approved | MASHEL JONGERT |
| Insulation | 11/4/2021 | Not Ready for Inspection | MASHEL JONGERT |
| Insulation | 11/8/2021 | Approved | MASHEL JONGERT |
| Drywall Nailing | 11/12/2021 | Approved | MASHEL JONGERT |
| BUILDING-Rough-Frame | 12/13/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 12/13/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 12/13/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 12/13/2021 | Approved | CHRIS CHRISTENSEN |
| Sewer | 2/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Sewer | 2/9/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 3/14/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| HVAC-Final | 3/14/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 3/18/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Special/Order Compliance | 3/18/2022 | Approved | ELMER BLAND |
| ELECTRICAL-Final | 3/25/2022 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 4/4/2022 | Approved | CRAIG DAVIS |
| HVAC-Final | 4/4/2022 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 4/4/2022 | Approved | CRAIG DAVIS |
| Final | 4/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Green Building Final | 4/21/2022 | Approved | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 4/21/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Service/Power Release | 4/21/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Smoke Detectors | 4/21/2022 | Approved | SHAVONNE ESPINOZA |
| Final | 4/25/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Service/Power Release | 4/25/2022 | Approved | SHAVONNE ESPINOZA |
| Final | 4/27/2022 | OK to Issue CofO | SHAVONNE ESPINOZA |
| PLUMBING-Final | 4/27/2022 | Approved | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Approved | SHAVONNE ESPINOZA |