530 N BEACHWOOD DR 90004

Certificate Information: 530 N BEACHWOOD DR 90004

Application / Permit
20010-20000-02520
Plan Check / Job No.
B20VN09756
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 16'-6" X 22'-6" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 6/22/2021
Issuing Office
Current Status
CofO Issued on 5/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 SELLA BENYAMIN
Corrections Issued 12/10/2020 SELLA BENYAMIN
Quality Review Completed 12/16/2020 STEVEN KIM
Building Plans Picked Up 12/16/2020 APPLICANT
Plan Check Approved 6/8/2021 SELLA BENYAMIN
Issued 6/22/2021 APPLICANT
CofO in Progress 4/28/2022 SHAVONNE ESPINOZA
Permit Finaled 5/16/2022 DEROLD HAUFF
CofO Issued 5/16/2022 DEROLD HAUFF
Permit Finaled 5/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/3/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/4/2021 JEANIE LAM
Sewer availability Cleared 3/4/2021 JEANIE LAM
Hydrant and Access approval Cleared 4/13/2021 MATTHEW CRAIG
Construction near power lines Cleared 5/20/2021 RIDWAN HARDY
Low Impact Development Cleared 5/27/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/1/2021 JEANIE LAM

Contact Information

Contractor Refined Home Construction Inc; Lic. No.: 1001310-B 113 N SAN VICENTE BLVD      BEVERLY HILLS, CA 90211
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/13/2021 Approved CHRIS CHRISTENSEN
METHANE-Barrier 8/13/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 8/13/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 8/13/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/5/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/15/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 10/15/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 10/15/2021 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 10/15/2021 Approved CHRIS CHRISTENSEN
Shower Pan 10/19/2021 Not Ready for Inspection MASHEL JONGERT
Interior/Exterior Lathing 10/22/2021 Partial Approval MASHEL JONGERT
Shower Pan 10/22/2021 Approved MASHEL JONGERT
Interior/Exterior Lathing 11/1/2021 Approved MASHEL JONGERT
Insulation 11/4/2021 Not Ready for Inspection MASHEL JONGERT
Insulation 11/8/2021 Approved MASHEL JONGERT
Drywall Nailing 11/12/2021 Approved MASHEL JONGERT
BUILDING-Rough-Frame 12/13/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 12/13/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 12/13/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 12/13/2021 Approved CHRIS CHRISTENSEN
Sewer 2/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Sewer 2/9/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 3/14/2022 Corrections Issued SHAVONNE ESPINOZA
HVAC-Final 3/14/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Final 3/18/2022 Partial Inspection SHAVONNE ESPINOZA
Special/Order Compliance 3/18/2022 Approved ELMER BLAND
ELECTRICAL-Final 3/25/2022 Approved ALIZAH MAYAGOITIA
Gas Test 4/4/2022 Approved CRAIG DAVIS
HVAC-Final 4/4/2022 Approved CRAIG DAVIS
PLUMBING-Final 4/4/2022 Approved CRAIG DAVIS
Final 4/21/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Green Building Final 4/21/2022 Approved SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV Not Ready SHAVONNE ESPINOZA
Service/Power Release 4/21/2022 Corrections Issued SHAVONNE ESPINOZA
Smoke Detectors 4/21/2022 Approved SHAVONNE ESPINOZA
Final 4/25/2022 Corrections Issued SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Not Ready SHAVONNE ESPINOZA
Service/Power Release 4/25/2022 Approved SHAVONNE ESPINOZA
Final 4/27/2022 OK to Issue CofO SHAVONNE ESPINOZA
PLUMBING-Final 4/27/2022 Approved SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Approved SHAVONNE ESPINOZA