10654 W NETTLETON ST 91352
Certificate Information: 10654 W NETTLETON ST 91352
- Application / Permit
- 20010-20000-02509
- Plan Check / Job No.
- B20VN09710
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22' X 47' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED PATIO
- Permit Issued
- Issued on 2/12/2021
- Issuing Office
- Current Status
- CofO Issued on 8/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2020 | SELLA BENYAMIN |
| Corrections Issued | 8/6/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 8/10/2020 | APPLICANT |
| Plan Check Approved | 12/28/2020 | SELLA BENYAMIN |
| Issued | 2/12/2021 | APPLICANT |
| CofO in Progress | 6/9/2022 | MATTHEW NELSON |
| CofO Issued | 8/23/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2020 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2020 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 9/25/2020 | ABDULLAH SADOZAI |
| Low Impact Development | Cleared | 11/9/2020 | SARAH YOUSSEF |
| Construction near power lines | Cleared | 11/20/2020 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 12/1/2020 | ABDULLAH SADOZAI |
Contact Information
| Contractor | D V Construction; Lic. No.: 1058728-B | 1201 N PACIFIC AVE #214 GLENDALE, CA 91202 |
| Engineer | Cardoza,, Jesse Adam; Lic. No.: C82846 | 6531 AMY AVENUE GARDEN GROVE, CA 92845 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/22/2021 | Partial Approval | BEAU COLLINS |
| Footing/Foundation/Slab | 3/2/2021 | Approved | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2021 | Approved | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2021 | Approved | BEAU COLLINS |
| HVAC-Rough | 4/16/2021 | Corrections Issued | BEAU COLLINS |
| Interior/Exterior Lathing | 4/28/2021 | Partial Approval | BEAU COLLINS |
| Rough-Elec/Plmb/HVAC | 4/28/2021 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 5/13/2021 | Partial Approval | DAVID MATSON |
| Green Building Rough | 5/13/2021 | Approved | DAVID MATSON |
| Insulation | 5/13/2021 | Approved | DAVID MATSON |
| Shower Pan | 5/13/2021 | Approved | DAVID MATSON |
| Drywall Nailing | 5/26/2021 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 5/26/2021 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/26/2021 | SGSOV Not Ready | JOHN HAYES |
| Underground Mechanical | 5/26/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/2/2021 | Approved | WILLIAM KUEHN |
| Final | 8/2/2021 | Corrections Issued | WILLIAM KUEHN |
| Green Building Final | 8/2/2021 | Approved | WILLIAM KUEHN |
| MERV13>=Final | 8/2/2021 | Approved | WILLIAM KUEHN |
| MERV13>=Rough | 8/2/2021 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 8/2/2021 | SGSOV Approved | WILLIAM KUEHN |
| Service/Power Release | 8/2/2021 | Approved | WILLIAM KUEHN |
| Smoke Detectors | 8/2/2021 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 8/2/2021 | Approved | WILLIAM KUEHN |
| Final | 1/28/2022 | Corrections Issued | JOHN HAYES |
| Final | 5/11/2022 | Partial Inspection | MATTHEW NELSON |
| Final | 6/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 6/8/2022 | OK to Issue CofO | MATTHEW NELSON |