10654 W NETTLETON ST 91352

Certificate Information: 10654 W NETTLETON ST 91352

Application / Permit
20010-20000-02509
Plan Check / Job No.
B20VN09710
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22' X 47' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED PATIO
Permit Issued
Issued on 2/12/2021
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2020 APPLICANT
Assigned to Plan Check Engineer 8/4/2020 SELLA BENYAMIN
Corrections Issued 8/6/2020 SELLA BENYAMIN
Building Plans Picked Up 8/10/2020 APPLICANT
Plan Check Approved 12/28/2020 SELLA BENYAMIN
Issued 2/12/2021 APPLICANT
CofO in Progress 6/9/2022 MATTHEW NELSON
CofO Issued 8/23/2022 DANIEL ORRANTE
Permit Finaled 8/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/24/2020 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 9/25/2020 ABDULLAH SADOZAI
Sewer availability Cleared 9/25/2020 ABDULLAH SADOZAI
Low Impact Development Cleared 11/9/2020 SARAH YOUSSEF
Construction near power lines Cleared 11/20/2020 RIDWAN HARDY
Roof/Waste drainage to street Cleared 12/1/2020 ABDULLAH SADOZAI

Contact Information

Contractor D V Construction; Lic. No.: 1058728-B 1201 N PACIFIC AVE   #214    GLENDALE, CA 91202
Engineer Cardoza,, Jesse Adam; Lic. No.: C82846 6531 AMY AVENUE      GARDEN GROVE, CA 92845

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/22/2021 Partial Approval BEAU COLLINS
Footing/Foundation/Slab 3/2/2021 Approved BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Approved BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 4/16/2021 Approved BEAU COLLINS
HVAC-Rough 4/16/2021 Corrections Issued BEAU COLLINS
Interior/Exterior Lathing 4/28/2021 Partial Approval BEAU COLLINS
Rough-Elec/Plmb/HVAC 4/28/2021 Approved BEAU COLLINS
BUILDING-Rough-Frame 5/13/2021 Partial Approval DAVID MATSON
Green Building Rough 5/13/2021 Approved DAVID MATSON
Insulation 5/13/2021 Approved DAVID MATSON
Shower Pan 5/13/2021 Approved DAVID MATSON
Drywall Nailing 5/26/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 5/26/2021 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/26/2021 SGSOV Not Ready JOHN HAYES
Underground Mechanical 5/26/2021 Approved JOHN HAYES
BUILDING-Rough-Frame 8/2/2021 Approved WILLIAM KUEHN
Final 8/2/2021 Corrections Issued WILLIAM KUEHN
Green Building Final 8/2/2021 Approved WILLIAM KUEHN
MERV13>=Final 8/2/2021 Approved WILLIAM KUEHN
MERV13>=Rough 8/2/2021 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 8/2/2021 SGSOV Approved WILLIAM KUEHN
Service/Power Release 8/2/2021 Approved WILLIAM KUEHN
Smoke Detectors 8/2/2021 Approved WILLIAM KUEHN
Verify Sprinkler Sign Off 8/2/2021 Approved WILLIAM KUEHN
Final 1/28/2022 Corrections Issued JOHN HAYES
Final 5/11/2022 Partial Inspection MATTHEW NELSON
Final 6/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 6/8/2022 OK to Issue CofO MATTHEW NELSON