14957 W GREENLEAF ST 91403

Certificate Information: 14957 W GREENLEAF ST 91403

Application / Permit
20010-20000-02500
Plan Check / Job No.
B20VN09653
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 21'-3" X 32'-1" GARAGE WITH ATTACHED STORAGE; 6'-1" X 10'-9" AND 3'-10" X 5'-4" PORCHES
Permit Issued
Issued on 5/21/2021
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 SELLA BENYAMIN
Corrections Issued 8/10/2020 SELLA BENYAMIN
Building Plans Picked Up 8/12/2020 APPLICANT
Plan Check Approved 4/30/2021 SELLA BENYAMIN
Issued 5/21/2021 APPLICANT
CofO in Progress 5/15/2025 JACK KARGODORIAN
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/25/2020 ADRIAN CASTRO
Low Impact Development Cleared 1/25/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/1/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/17/2021 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/5/2021 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 10/5/2021 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 5/26/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 6/30/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 7/1/2022 Partial Approval JACK KARGODORIAN
Drywall Nailing 9/2/2022 Approved ASHLEY THOMPSON
Insulation 9/2/2022 Approved ASHLEY THOMPSON
Pre-Inspection 10/27/2023 Not Ready for Inspection THOMAS FINNILA
Final 5/2/2025 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 5/2/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved JACK KARGODORIAN
Service/Power Release 5/2/2025 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 5/2/2025 Approved JACK KARGODORIAN
Final 5/14/2025 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 5/14/2025 Approved JACK KARGODORIAN