6328 N LANGDON AVE 91411
Certificate Information: 6328 N LANGDON AVE 91411
- Application / Permit
- 20010-20000-02477
- Plan Check / Job No.
- B20VN09593
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 34'-0" X 25'-0" DETACHED ACCESSORY DWELLING UNIT PER WFPP
- Permit Issued
- Issued on 2/25/2021
- Issuing Office
- Current Status
- CofO Issued on 8/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 8/2/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 2/4/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/9/2021 | JEROME MAGAT PALMA |
| Issued | 2/25/2021 | APPLICANT |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| CofO in Progress | 8/12/2022 | RICHARD DOCKUS |
| Permit Finaled | 8/12/2022 | DANIEL ORRANTE |
| CofO Issued | 8/12/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/12/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/7/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 8/12/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 11/20/2020 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/21/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 1/21/2021 | ANDRES COVARRUBIAS |
| ZI | Cleared | 2/4/2021 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 2/5/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/23/2021 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 3/23/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Underground Mechanical | 3/23/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 4/14/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/14/2021 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/28/2021 | Approved | MICHEL ABAJAN |
| Sewer | 6/2/2021 | Corrections Issued | MICHAEL TEMPLE |
| Sewer | 6/3/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/5/2021 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 10/5/2021 | Corrections Issued | RICHARD DOCKUS |
| Green Building Rough | 10/5/2021 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 10/5/2021 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 10/5/2021 | Approved | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 10/5/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 10/19/2021 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 10/19/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 10/19/2021 | Approved | RAUL OLAGI |
| Special/Order Compliance | 10/19/2021 | Corrections Issued | RAUL OLAGI |
| Verify Sprinkler Sign Off | 10/19/2021 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/1/2021 | Corrections Issued | RICHARD DOCKUS |
| Insulation | 11/5/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 11/5/2021 | Partial Approval | RICHARD DOCKUS |
| Drywall Nailing | 11/18/2021 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/8/2022 | Approved | RICHARD DOCKUS |
| Final | 3/8/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 3/8/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Service/Power Release | 3/8/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 3/8/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| ELECTRICAL-Final | 5/4/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 5/4/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 5/4/2022 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 5/4/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 6/15/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 6/15/2022 | Approved | RICHARD DOCKUS |
| Final | 7/14/2022 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 7/14/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 8/2/2022 | Corrections Issued | RICHARD DOCKUS |
| Gas Test | 8/2/2022 | Approved | RICHARD DOCKUS |
| Final | 8/9/2022 | OK to Issue CofO | RICHARD DOCKUS |
| Service/Power Release | 8/9/2022 | Approved | RICHARD DOCKUS |