9313 N SHARP AVE 91331
Certificate Information: 9313 N SHARP AVE 91331
- Application / Permit
- 20010-20000-02474
- Plan Check / Job No.
- B20VN09587
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED (36'X31') DETACHED ACCESSORY DWELLING UNIT W/ PORCH (3'X11') PER ENGR DESIGN. SEE COMMENTS.
- Permit Issued
- Issued on 1/27/2021
- Issuing Office
- Current Status
- CofO Issued on 12/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 8/4/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 12/30/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 1/14/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/27/2021 | HAYATO TSUCHIYA |
| Issued | 1/27/2021 | APPLICANT |
| CofO in Progress | 12/7/2022 | MICHEL ABAJAN |
| CofO Issued | 12/8/2022 | RONALD MYRICK |
| Permit Finaled | 12/8/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/11/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 10/16/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/20/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/22/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/18/2021 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/4/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/25/2021 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/25/2021 | Partial Inspection | MICHEL ABAJAN |
| Green Building Rough | 3/25/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/25/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/25/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/30/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/30/2021 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/30/2021 | Approved | MICHEL ABAJAN |
| Insulation | 4/1/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/5/2021 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 4/30/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/30/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/30/2021 | Approved | MICHEL ABAJAN |
| Final | 7/30/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/30/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 7/30/2021 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 7/30/2021 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 7/30/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/30/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/30/2021 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 7/30/2021 | Corrections Issued | MICHEL ABAJAN |
| Smoke Detectors | 7/30/2021 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 7/30/2021 | Approved | MICHEL ABAJAN |
| Final | 10/18/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 10/18/2021 | Approved | MICHEL ABAJAN |
| Service/Power Release | 10/18/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 9/12/2022 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 9/12/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 11/28/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 11/28/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 12/7/2022 | OK to Issue CofO | MICHEL ABAJAN |
| PLUMBING-Final | 12/7/2022 | Approved | MICHEL ABAJAN |
| Service/Power Release | 12/7/2022 | Approved | MICHEL ABAJAN |