9313 N SHARP AVE 91331

Certificate Information: 9313 N SHARP AVE 91331

Application / Permit
20010-20000-02474
Plan Check / Job No.
B20VN09587
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED (36'X31') DETACHED ACCESSORY DWELLING UNIT W/ PORCH (3'X11') PER ENGR DESIGN. SEE COMMENTS.
Permit Issued
Issued on 1/27/2021
Issuing Office
Current Status
CofO Issued on 12/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2020 APPLICANT
Assigned to Plan Check Engineer 7/31/2020 HAYATO TSUCHIYA
Corrections Issued 8/4/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 12/30/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 1/14/2021 HAYATO TSUCHIYA
Plan Check Approved 1/27/2021 HAYATO TSUCHIYA
Issued 1/27/2021 APPLICANT
CofO in Progress 12/7/2022 MICHEL ABAJAN
CofO Issued 12/8/2022 RONALD MYRICK
Permit Finaled 12/8/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 8/10/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/11/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/11/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 10/16/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/20/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/22/2020 JOHN TRIANTAFYLLOS

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/18/2021 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 3/4/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 3/25/2021 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 3/25/2021 Partial Inspection MICHEL ABAJAN
Green Building Rough 3/25/2021 Approved MICHEL ABAJAN
HVAC-Rough 3/25/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 3/25/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/30/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/30/2021 Approved MICHEL ABAJAN
Shower Pan 3/30/2021 Approved MICHEL ABAJAN
Insulation 4/1/2021 Approved MICHEL ABAJAN
Drywall Nailing 4/5/2021 Approved MICHEL ABAJAN
Underground Mechanical 4/30/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/30/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/30/2021 Approved MICHEL ABAJAN
Final 7/30/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 7/30/2021 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 7/30/2021 Approved MICHEL ABAJAN
MERV13>=Final 7/30/2021 Approved MICHEL ABAJAN
MERV13>=Rough 7/30/2021 Approved MICHEL ABAJAN
PLUMBING-Final 7/30/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/30/2021 SGSOV Approved MICHEL ABAJAN
Service/Power Release 7/30/2021 Corrections Issued MICHEL ABAJAN
Smoke Detectors 7/30/2021 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 7/30/2021 Approved MICHEL ABAJAN
Final 10/18/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 10/18/2021 Approved MICHEL ABAJAN
Service/Power Release 10/18/2021 Not Ready for Inspection MICHEL ABAJAN
Final 9/12/2022 Corrections Issued MICHEL ABAJAN
Service/Power Release 9/12/2022 Not Ready for Inspection MICHEL ABAJAN
Final 11/28/2022 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 11/28/2022 Not Ready for Inspection MICHEL ABAJAN
Final 12/7/2022 OK to Issue CofO MICHEL ABAJAN
PLUMBING-Final 12/7/2022 Approved MICHEL ABAJAN
Service/Power Release 12/7/2022 Approved MICHEL ABAJAN