150 N CARONDELET ST #1 90026

Certificate Information: 150 N CARONDELET ST #1 90026

Application / Permit
20010-20000-02444
Plan Check / Job No.
B20VN09479
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSE THREE STORY 5 UNITS TOWNHOUSE WITH ATTACH GARAGE_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 10/23/2023
Issuing Office
Valley
Current Status
Issued on 10/23/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/21/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 DAWN MC NULTY
Corrections Issued 8/5/2020 DAWN MC NULTY
Quality Review Completed 8/5/2020 CHON CHIO KUO
Building Plans Picked Up 8/6/2020 APPLICANT
Disabled Access Plans Picked Up 8/6/2020 APPLICANT
Green Plans Picked Up 8/6/2020 APPLICANT
Applicant returned to address corrections 3/16/2022 DAWN MC NULTY
Applicant returned to address corrections 6/22/2022 DAWN MC NULTY
Applicant returned to address corrections 9/7/2023 DAWN MC NULTY
Plan Check Approved 10/23/2023 DAWN MC NULTY
Issued 10/23/2023 APPLICANT

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 3/17/2021 STEVEN WECHSLER
Address approval Cleared 7/20/2021 WALLIE JONG
Highway dedication Cleared 7/21/2021 CECILIO NAVARRO
Permit Cleared 10/26/2021 THAN WIN
Low Impact Development Cleared 10/29/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/28/2021 WALLIE JONG
Sewer availability Cleared 1/11/2022 WALLIE JONG
Hydrant and Access approval Cleared 1/20/2022 KURT CORRAL
GPI Written Notices Cleared 3/16/2022 DAWN MC NULTY
Grading Pre-Inspection Cleared 3/16/2022 DAWN MC NULTY
Miscellaneous Cleared 3/16/2022 DAWN MC NULTY
Construction near power lines Cleared 4/22/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/14/2023 AMAAN MALIK
Green Code Cleared 2/22/2023 AARON COSTA
DAS Clearance Cleared 10/6/2023 NORLITO MEDRANO

Contact Information

Contractor Iconic Development; Lic. No.: 989768-B 10073 VALLEY VIEW ST #272      CYPRESS, CA 90630
Engineer Esmaily-Radvar,, Shahrokh; Lic. No.: GE2742 5 HODGENVILLE      IRVINE, CA 92620
Engineer Hakemi,, Fahim; Lic. No.: C64784 26982 MARBELLA      MISSION VIEJO, CA 92691

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2024 Approved EDWIN GREGORYONA
Masonry Wall/Backfill 3/25/2024 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 4/2/2024 Corrections Issued NICK DANERI
Footing/Foundation/Slab 5/21/2024 Not Ready for Inspection NICK DANERI
METHANE-Barrier 5/21/2024 Approved NICK DANERI
METHANE-Subgrade 5/21/2024 Approved NICK DANERI
Footing/Foundation/Slab 5/29/2024 Not Ready for Inspection NICK DANERI
Special/Order Compliance 5/30/2024 Partial Approval NICK DANERI
Footing/Foundation/Slab 6/10/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/18/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 7/25/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval NICK DANERI
Pre-Inspection 9/6/2024 Not Ready for Inspection LUIS CCAMACHO
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/29/2024 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 11/12/2024 Not Ready for Inspection NICK DANERI
Interior/Exterior Lathing 11/25/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/3/2024 Partial Approval NICK DANERI
Green Building Rough 12/20/2024 Not Ready for Inspection NICK DANERI
METHANE-Rough 12/20/2024 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 12/20/2024 Not Ready for Inspection NICK DANERI
Wood Frame 12/20/2024 Partial Approval NICK DANERI
Insulation 12/26/2024 Approved NICK DANERI
Drywall Nailing 1/10/2025 Approved NICK DANERI
Pre-Inspection 4/11/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 8/26/2025 Corrections Issued ERNESTO CORRAL
Pre-Inspection 9/29/2025 Not Ready for Inspection JOEY BUCHANAN
Final 10/31/2025 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 10/31/2025 Approved JOEY BUCHANAN
Green Building Final 10/31/2025 Approved JOEY BUCHANAN
Green Building Rough 10/31/2025 Approved JOEY BUCHANAN
METHANE-Final 10/31/2025 Approved JOEY BUCHANAN
METHANE-Rough 10/31/2025 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 10/31/2025 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 10/31/2025 Approved JOEY BUCHANAN
Wood Frame 10/31/2025 Approved JOEY BUCHANAN
Special/Order Compliance 11/18/2025 Approved JOEY BUCHANAN
Pre-Inspection 7/10/2026 Not Ready for Inspection RAFAEL CORTES
Special/Order Compliance 7/14/2026 Approved JOEY BUCHANAN