12435 W BROMWICH ST 91331
Certificate Information: 12435 W BROMWICH ST 91331
- Application / Permit
- 20010-20000-02435
- Plan Check / Job No.
- B20VN09439
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 42'-0" X 30'-0" DETACHED ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 12/6/2020
- Issuing Office
- Current Status
- CofO Issued on 10/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 7/26/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 11/17/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/4/2020 | JEROME MAGAT PALMA |
| Issued | 12/6/2020 | APPLICANT |
| CofO in Progress | 9/17/2021 | MICHEL ABAJAN |
| CofO Issued | 10/19/2021 | MICHAEL SMITH |
| Permit Finaled | 10/19/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2020 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 10/21/2020 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 11/9/2020 | SARAH YOUSSEF |
| Zoning Information File | Cleared | 11/18/2020 | JEROME MAGAT PALMA |
| Roof/Waste drainage to street | Cleared | 11/23/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 12/1/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 329 N HUBBARD AVE SAN FERNANDO, CA 91340 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/15/2020 | Corrections Issued | MICHEL ABAJAN |
| Deputy Steel/Welding | 12/18/2020 | No Access for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 12/22/2020 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 12/24/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/11/2021 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 1/11/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 1/11/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/15/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 1/15/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/13/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/13/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/13/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/13/2021 | Approved | MICHEL ABAJAN |
| Wood Frame | 4/13/2021 | Approved | MICHEL ABAJAN |
| Insulation | 4/22/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/28/2021 | Approved | MICHEL ABAJAN |
| Sewer | 4/28/2021 | Approved | MICHEL ABAJAN |
| Shower Pan | 5/4/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/4/2021 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/4/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/4/2021 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/8/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/23/2021 | Approved | MICHEL ABAJAN |
| Final | 6/23/2021 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/23/2021 | Approved | MICHEL ABAJAN |
| Green Building Final | 6/23/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/23/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2021 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 6/23/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 6/23/2021 | Approved | MICHEL ABAJAN |
| Final | 8/27/2021 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 8/27/2021 | Approved | MICHEL ABAJAN |
| Final | 9/17/2021 | OK to Issue CofO | MICHEL ABAJAN |