4130 N HAYVENHURST AVE 91436

Certificate Information: 4130 N HAYVENHURST AVE 91436

Application / Permit
20010-20000-02431
Plan Check / Job No.
B20VN09436
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 2/17/2021
Issuing Office
Valley
Current Status
CofO Issued on 11/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 NILOOFAR MEHRAIN
Corrections Issued 8/27/2020 NILOOFAR MEHRAIN
Quality Review Completed 8/31/2020 CHON CHIO KUO
Building Plans Picked Up 9/2/2020 APPLICANT
Applicant returned to address corrections 11/17/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/12/2021 NILOOFAR MEHRAIN
Plan Check Approved 1/19/2021 NILOOFAR MEHRAIN
Issued 2/17/2021 APPLICANT
CofO in Progress 11/10/2022 SEAN WIRCH
Permit Finaled 11/10/2022 JOHN JANSON
CofO Issued 11/10/2022 JOHN JANSON
Permit Finaled 11/10/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/11/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 9/11/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 9/11/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 9/11/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 9/11/2020 ADRIAN CASTRO
Street Frontage Cleared 9/11/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/15/2020 ADRIAN CASTRO
Sewer availability Cleared 9/15/2020 ADRIAN CASTRO
Trees in Parkway Cleared 9/22/2020 JOHN KIM
BHO/Hillside ordinance Cleared 10/15/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 11/3/2020 MATTHEW CRAIG
Low Impact Development Cleared 11/4/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 11/5/2020 ADRIAN CASTRO
Excavation more than 5-ft deep Cleared 11/17/2020 CALOSHA APPROVED
GPI Written Notices Cleared 11/17/2020 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 11/17/2020 NILOOFAR MEHRAIN
Construction near power lines Cleared 12/18/2020 WALTER RAMIREZ
Construction within easement Cleared 12/18/2020 WALTER RAMIREZ
Green Code Cleared 1/19/2021 NILOOFAR MEHRAIN
Haul Route Cleared 1/19/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/24/2021 Corrections Issued RONALD COWAN
Excavation/Setback/Form/Re-Bar 3/30/2021 Corrections Issued RONALD COWAN
Excavation/Setback/Form/Re-Bar 4/5/2021 Partial Approval RONALD COWAN
Excavation/Setback/Form/Re-Bar 4/9/2021 Not Ready for Inspection MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 4/29/2021 Approved RONALD COWAN
Deputy Shotcrete 5/3/2021 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/3/2021 No Access for Inspection STEVEN BACK
Deputy Steel/Welding 5/18/2021 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 5/19/2021 Partial Approval RONALD COWAN
Sewer 6/3/2021 Approved RONALD COWAN
Sewer 6/4/2021 Approved RONALD COWAN
Deputy Steel/Welding 6/14/2021 Approved RONALD COWAN
Underground Mechanical 6/16/2021 Partial Approval DAVID SANDOVAL
Wood Frame 6/16/2021 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 6/23/2021 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 6/23/2021 Partial Approval PETER FOLLING
Green Building Rough 6/23/2021 Not Ready for Inspection PETER FOLLING
Verify Sprinkler Sign Off 6/23/2021 Not Ready for Inspection PETER FOLLING
Deputy Steel/Welding 8/6/2021 Approved RONALD COWAN
Wood Frame 8/12/2021 Partial Approval RONALD COWAN
Wood Frame 9/10/2021 Corrections Issued RONALD COWAN
Wood Frame 10/20/2021 Partial Approval RONALD COWAN
Wood Frame 10/26/2021 Not Ready for Inspection PETER FOLLING
Wood Frame 10/28/2021 Not Ready for Inspection PETER FOLLING
HVAC-Rough 11/4/2021 Approved RONALD COWAN
Wood Frame 11/4/2021 Partial Approval RONALD COWAN
ELECTRICAL-Rough 11/10/2021 Approved RONALD COWAN
PLUMBING-Rough 11/10/2021 Approved RONALD COWAN
ELECTRICAL-Rough 11/16/2021 Approved ROBERT GOLD
PLUMBING-Rough 11/16/2021 Approved ROBERT GOLD
Wood Frame 11/16/2021 Partial Inspection ROBERT GOLD
Insulation 11/23/2021 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 11/23/2021 Partial Approval JAVIER RAMOS JR
Shower Pan 11/23/2021 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 12/3/2021 Approved DAVID SANDOVAL
Shower Pan 12/3/2021 Approved DAVID SANDOVAL
Drywall Nailing 12/7/2021 Approved DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 12/20/2021 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 12/27/2021 No Access for Inspection VINCENT HANLEY
Masonry Wall/Backfill 12/30/2021 Not Ready for Inspection PETER FOLLING
Masonry Wall/Backfill 1/3/2022 Partial Approval DAVID SANDOVAL
Special/Order Compliance 1/3/2022 Corrections Issued DAVID SANDOVAL
Masonry Wall/Backfill 1/19/2022 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 1/21/2022 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 2/18/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 3/10/2022 Corrections Issued DAVID SANDOVAL
Green Building Rough 3/10/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 3/10/2022 Not Ready for Inspection DAVID SANDOVAL
Verify Sprinkler Sign Off 3/10/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 3/14/2022 Not Ready for Inspection DAVID SANDOVAL
Gas Test 8/8/2022 Approved VINCENT HANLEY
Enclosure/Fence 8/17/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/19/2022 Approved VINCENT HANLEY
Final 9/19/2022 Corrections Issued VINCENT HANLEY
Green Building Final 9/19/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 9/19/2022 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 9/19/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 11/4/2022 Approved VINCENT HANLEY
Final 11/4/2022 Corrections Issued VINCENT HANLEY
Gas Test 11/4/2022 Approved VINCENT HANLEY
HVAC-Final 11/4/2022 Approved VINCENT HANLEY
PLUMBING-Final 11/4/2022 Approved VINCENT HANLEY
Service/Power Release 11/4/2022 Not Ready for Inspection VINCENT HANLEY
Final 11/14/2022 OK to Issue CofO SEAN WIRCH
Service/Power Release 11/14/2022 Approved SEAN WIRCH