13013 W WILLARD ST 91605
Certificate Information: 13013 W WILLARD ST 91605
- Application / Permit
- 20010-20000-02429
- Plan Check / Job No.
- B20VN09434
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ADU
- Permit Issued
- Issued on 3/15/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | RODNEY SAMIIAN |
| Corrections Issued | 8/13/2020 | RODNEY SAMIIAN |
| Quality Review Completed | 8/14/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/20/2020 | APPLICANT |
| Plan Check Approved | 3/15/2021 | RODNEY SAMIIAN |
| Issued | 3/15/2021 | APPLICANT |
| CofO in Progress | 5/24/2022 | DAVID MATSON |
| CofO in Progress | 5/24/2022 | DAVID MATSON |
| Permit Finaled | 8/20/2022 | DANIEL ORRANTE |
| CofO Issued | 8/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 8/28/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 10/28/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/17/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/22/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 1/26/2021 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wassef,, Mena Maher Salama; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/14/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/24/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 5/24/2021 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 6/14/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 6/14/2021 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 7/9/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/29/2021 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 8/27/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/24/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 9/24/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 9/24/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/24/2021 | Partial Approval | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 9/24/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/5/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 10/5/2021 | Approved | GREGG CUMMINGS |
| Insulation | 10/13/2021 | Approved | ASHLEY THOMPSON |
| Shower Pan | 10/13/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 10/18/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/25/2021 | Approved | MATTHEW NELSON |
| Shower Pan | 10/25/2021 | Approved | MATTHEW NELSON |
| Sewer | 12/27/2021 | Corrections Issued | GREGG CUMMINGS |
| Sewer | 1/3/2022 | Approved | WILLIAM WREN |
| Underground Mechanical | 1/3/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 1/10/2022 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 3/15/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/13/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 5/4/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 5/4/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 5/4/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 5/4/2022 | Approved | GREGG CUMMINGS |
| Final | 5/18/2022 | Corrections Issued | DAVID MATSON |
| Pre-Inspection | 5/18/2022 | Corrections Issued | DAVID MATSON |
| BUILDING-Rough-Frame | 5/23/2022 | Approved | DAVID MATSON |
| Final | 5/23/2022 | OK to Issue CofO | DAVID MATSON |
| Service/Power Release | 5/23/2022 | Approved | DAVID MATSON |