8219 N ST CLAIR AVE 91605
Certificate Information: 8219 N ST CLAIR AVE 91605
- Application / Permit
- 20010-20000-02417
- Plan Check / Job No.
- B20VN09404
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 58' X 21'-10" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER WFPP.
- Permit Issued
- Issued on 6/17/2021
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2020 | ROSENDO MEDINA |
| Corrections Issued | 7/27/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 6/15/2021 | ROSENDO MEDINA |
| Plan Check Approved | 6/16/2021 | ROSENDO MEDINA |
| Issued | 6/17/2021 | APPLICANT |
| Building Plans Picked Up | 6/17/2021 | APPLICANT |
| CofO in Progress | 3/4/2022 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/21/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2020 | JOHN TRIANTAFYLLOS |
| Miscellaneous | Cleared | 12/21/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/21/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 1/22/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 4/17/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/14/2021 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 5/25/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/24/2021 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/6/2021 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/8/2021 | Approved | JOHN HAYES |
| Underground Mechanical | 7/15/2021 | Partial Inspection | JOHN HAYES |
| Wood Frame | 7/15/2021 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 7/28/2021 | Partial Approval | JOHN HAYES |
| Green Building Rough | 7/28/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 7/28/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/5/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 8/5/2021 | Approved | JOHN HAYES |
| Green Building Rough | 8/5/2021 | Approved | JOHN HAYES |
| HVAC-Rough | 8/5/2021 | Approved | JOHN HAYES |
| PLUMBING-Rough | 8/5/2021 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 8/5/2021 | Approved | JOHN HAYES |
| Insulation | 8/13/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/13/2021 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 9/8/2021 | Approved | JUSTIN HAWLEY |
| Shower Pan | 10/4/2021 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 10/21/2021 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 2/23/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 2/23/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 2/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Final | 2/23/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 2/23/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 2/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 2/23/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 2/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 3/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 3/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 3/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 3/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 3/4/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/4/2022 | Approved | CHRISTOPHER DELLEFIELD |