8219 N ST CLAIR AVE 91605

Certificate Information: 8219 N ST CLAIR AVE 91605

Application / Permit
20010-20000-02417
Plan Check / Job No.
B20VN09404
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 58' X 21'-10" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER WFPP.
Permit Issued
Issued on 6/17/2021
Issuing Office
Current Status
CofO Issued on 5/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/27/2020 ROSENDO MEDINA
Corrections Issued 7/27/2020 ROSENDO MEDINA
Applicant returned to address corrections 6/15/2021 ROSENDO MEDINA
Plan Check Approved 6/16/2021 ROSENDO MEDINA
Issued 6/17/2021 APPLICANT
Building Plans Picked Up 6/17/2021 APPLICANT
CofO in Progress 3/4/2022 CHRISTOPHER DELLEFIELD
CofO Issued 5/14/2022 MICHAEL SMITH
Permit Finaled 5/14/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/21/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/21/2020 JOHN TRIANTAFYLLOS
Miscellaneous Cleared 12/21/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/21/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 1/22/2021 MATTHEW CRAIG
Construction near power lines Cleared 4/17/2021 RIDWAN HARDY
Low Impact Development Cleared 5/14/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 5/25/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/24/2021 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 7/6/2021 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 7/8/2021 Approved JOHN HAYES
Underground Mechanical 7/15/2021 Partial Inspection JOHN HAYES
Wood Frame 7/15/2021 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 7/28/2021 Partial Approval JOHN HAYES
Green Building Rough 7/28/2021 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 7/28/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 8/5/2021 Approved JOHN HAYES
ELECTRICAL-Rough 8/5/2021 Approved JOHN HAYES
Green Building Rough 8/5/2021 Approved JOHN HAYES
HVAC-Rough 8/5/2021 Approved JOHN HAYES
PLUMBING-Rough 8/5/2021 Approved JOHN HAYES
Verify Sprinkler Sign Off 8/5/2021 Approved JOHN HAYES
Insulation 8/13/2021 Approved JOHN HAYES
Interior/Exterior Lathing 8/13/2021 Partial Approval JOHN HAYES
Drywall Nailing 9/8/2021 Approved JUSTIN HAWLEY
Shower Pan 10/4/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/21/2021 SGSOV Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/23/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 2/23/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 2/23/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Final 2/23/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 2/23/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 2/23/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 2/23/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Service/Power Release 2/23/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 2/23/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 3/1/2022 Approved CHRISTOPHER DELLEFIELD
Final 3/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 3/1/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 3/1/2022 Approved CHRISTOPHER DELLEFIELD
Service/Power Release 3/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 3/4/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
Service/Power Release 3/4/2022 Approved CHRISTOPHER DELLEFIELD