7902 W FORSYTHE ST 91040

Certificate Information: 7902 W FORSYTHE ST 91040

Application / Permit
20010-20000-02414
Plan Check / Job No.
B20VN09392
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22'0-3/4"X30-9" IRREGULAR SHAPED 2-STORY ADU PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
CofO Issued on 7/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 MARVEL DELACRUZ
Corrections Issued 8/18/2020 MARVEL DELACRUZ
Quality Review Completed 8/20/2020 STEVEN KIM
Building Plans Picked Up 8/21/2020 APPLICANT
Applicant returned to address corrections 5/25/2021 MARVEL DELACRUZ
Applicant returned to address corrections 6/4/2021 MARVEL DELACRUZ
Plan Check Approved 6/7/2021 MARVEL DELACRUZ
Issued 6/8/2021 APPLICANT
CofO in Progress 7/19/2024 WILLIAM WREN
Permit Finaled 7/25/2024 RUBEN SALAS
CofO Issued 7/25/2024 RUBEN SALAS
Permit Finaled 7/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/30/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 10/8/2020 MATTHEW CRAIG
Grading Pre-Inspection Cleared 11/24/2020 BRIAN MILLER
Low Impact Development Cleared 3/2/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/8/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/12/2021 GABRIEL ROBLES
GPI Written Notices Cleared 5/12/2021 MARVEL DELACRUZ
Sewer availability Cleared 5/12/2021 GABRIEL ROBLES
Green Code Cleared 6/4/2021 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/22/2021 Conditional Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/17/2021 Partial Approval MATTHEW NELSON
Green Building Rough 11/17/2021 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 11/17/2021 Partial Approval MATTHEW NELSON
Verify Sprinkler Sign Off 11/17/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 11/29/2021 Partial Approval MATTHEW NELSON
Green Building Rough 11/29/2021 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 11/29/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 12/6/2021 Partial Approval MATTHEW NELSON
Green Building Rough 12/6/2021 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 12/6/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 1/5/2022 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 1/5/2022 Approved MATTHEW NELSON
Green Building Rough 1/5/2022 Approved MATTHEW NELSON
HVAC-Rough 1/5/2022 Corrections Issued MATTHEW NELSON
Interior/Exterior Lathing 1/5/2022 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 1/5/2022 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 1/5/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/10/2022 Approved MATTHEW NELSON
HVAC-Rough 1/10/2022 Approved MATTHEW NELSON
Insulation 1/11/2022 Not Ready for Inspection MATTHEW NELSON
Insulation 1/13/2022 No Access for Inspection KRISTEN CAUSEY
Drywall Nailing 1/14/2022 Corrections Issued KRISTEN CAUSEY
Interior/Exterior Lathing 1/14/2022 No Access for Inspection KRISTEN CAUSEY
Drywall Nailing 1/19/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/19/2022 Approved MATTHEW NELSON
Shower Pan 1/19/2022 Approved MATTHEW NELSON
Final 7/10/2024 No Access for Inspection WILLIAM WREN
Footing/Foundation/Slab 7/10/2024 Not Ready for Inspection WILLIAM WREN
Green Building Final 7/10/2024 No Access for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 7/10/2024 SGSOV Not Ready WILLIAM WREN
Service/Power Release 7/10/2024 Not Ready for Inspection WILLIAM WREN
Smoke Detectors 7/10/2024 Not Ready for Inspection WILLIAM WREN
Pre-Inspection 7/15/2024 Corrections Issued WILLIAM WREN
Final 7/17/2024 OK to Issue CofO WILLIAM WREN
Footing/Foundation/Slab 7/17/2024 Approved WILLIAM WREN
Green Building Final 7/17/2024 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 7/17/2024 SGSOV Approved WILLIAM WREN
Service/Power Release 7/17/2024 Approved WILLIAM WREN
Smoke Detectors 7/17/2024 Approved WILLIAM WREN