11931 W ARMINTA ST 91605
Certificate Information: 11931 W ARMINTA ST 91605
- Application / Permit
- 20010-20000-02399
- Plan Check / Job No.
- B20VN09336
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (28'-0"x 37'-6") DETACHED ONE STORY ACCESSORY DWELLING UNIT WITH ATTACHED (200 SF) COVERED PATIO PER LAMC 12.22 A.33 (c) and (d). WORK PER LA WFPP STD PLAN.
- Permit Issued
- Issued on 6/30/2021
- Issuing Office
- Current Status
- CofO Issued on 12/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | TROY DEGUZMAN |
| Corrections Issued | 7/23/2020 | TROY DEGUZMAN |
| Building Plans Picked Up | 8/25/2020 | APPLICANT |
| Plan Check Approved | 6/29/2021 | TROY DEGUZMAN |
| Issued | 6/30/2021 | APPLICANT |
| CofO in Progress | 12/6/2022 | MATTHEW NELSON |
| Permit Finaled | 12/20/2022 | MICHAEL SMITH |
| CofO Issued | 12/20/2022 | MICHAEL SMITH |
| Permit Finaled | 12/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/4/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 9/29/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/5/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 1/6/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/7/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/8/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/12/2021 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 7/15/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/27/2021 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 7/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 8/3/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 8/4/2021 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 8/5/2021 | Approved | JOHN HAYES |
| Underground Mechanical | 8/5/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 8/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 9/29/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 9/29/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 9/30/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 10/7/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 10/7/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/7/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 10/7/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 10/7/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 10/7/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/18/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 10/18/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 10/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 10/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 10/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 11/1/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 11/1/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 11/1/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 4/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 5/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 7/12/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 7/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 9/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 9/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Final | 9/22/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 9/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 9/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 9/22/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 9/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 12/5/2022 | Approved | MATTHEW NELSON |
| Final | 12/5/2022 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 12/5/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 12/5/2022 | Approved | MATTHEW NELSON |
| Service/Power Release | 12/5/2022 | Approved | MATTHEW NELSON |