5024 N GREENBUSH AVE 91423

Certificate Information: 5024 N GREENBUSH AVE 91423

Application / Permit
20010-20000-02380
Plan Check / Job No.
B20VN09276
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 13'X 19'-6" REC ROOM
Permit Issued
Issued on 2/11/2021
Issuing Office
Current Status
CofO Issued on 10/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 SELLA BENYAMIN
Corrections Issued 8/10/2020 SELLA BENYAMIN
Quality Review Completed 8/13/2020 STEVEN KIM
Building Plans Picked Up 8/14/2020 APPLICANT
Plan Check Approved 12/1/2020 SELLA BENYAMIN
Issued 2/11/2021 APPLICANT
CofO in Progress 10/12/2021 MICHEL ABAJAN
Permit Finaled 10/19/2021 MICHAEL SMITH
CofO Issued 10/19/2021 MICHAEL SMITH
Permit Finaled 10/19/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/26/2020 GABRIEL ROBLES
Low Impact Development Cleared 10/13/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/19/2020 GABRIEL ROBLES
Construction near power lines Cleared 11/6/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/23/2021 Approved JOHN HAYES
Footing/Foundation/Slab 3/5/2021 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Approval DANIEL DREW
Wood Frame 3/26/2021 Approved DANIEL DREW
ELECTRICAL-Rough 4/22/2021 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 4/22/2021 Approved CHARLES POWELL
HVAC-Rough 4/22/2021 Approved CHARLES POWELL
PLUMBING-Rough 4/22/2021 Corrections Issued CHARLES POWELL
Shower Pan 4/29/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/5/2021 Conditional Approval MISAEL ESPARZA
ELECTRICAL-Final 10/5/2021 Corrections Issued MISAEL ESPARZA
Final 10/5/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 10/5/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 10/5/2021 Approved MISAEL ESPARZA
HVAC-Final 10/5/2021 Approved MISAEL ESPARZA
PLUMBING-Final 10/5/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/5/2021 SGSOV Approved MISAEL ESPARZA
Service/Power Release 10/5/2021 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 10/5/2021 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 10/5/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/12/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 10/12/2021 Approved MICHEL ABAJAN
Final 10/12/2021 OK to Issue CofO MICHEL ABAJAN
Green Building Final 10/12/2021 Approved MICHEL ABAJAN
HVAC-Final 10/12/2021 Approved MICHEL ABAJAN
Service/Power Release 10/12/2021 Approved MICHEL ABAJAN
Smoke Detectors 10/12/2021 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 10/12/2021 Approved MICHEL ABAJAN