5024 N GREENBUSH AVE 91423

Certificate Information: 5024 N GREENBUSH AVE 91423

Application / Permit
20010-20000-02379
Plan Check / Job No.
B20VN09276
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 39'-4" X 64'-3" (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/23/2021
Issuing Office
Current Status
CofO Issued on 10/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 SELLA BENYAMIN
Corrections Issued 8/10/2020 SELLA BENYAMIN
Quality Review Completed 8/13/2020 STEVEN KIM
Building Plans Picked Up 8/14/2020 APPLICANT
Plan Check Approved 12/1/2020 SELLA BENYAMIN
Issued 2/23/2021 APPLICANT
CofO in Progress 10/12/2021 MICHEL ABAJAN
Permit Finaled 10/19/2021 MICHAEL SMITH
CofO Issued 10/19/2021 MICHAEL SMITH
Permit Finaled 10/19/2021 MICHAEL SMITH

Permit Application Clearance Information

Permit Cleared 8/25/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/26/2020 GABRIEL ROBLES
Sewer availability Cleared 8/26/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/2/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/13/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/19/2020 GABRIEL ROBLES
Trees in Parkway Cleared 11/16/2020 JOHN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/4/2021 Approved CHARLES POWELL
Footing/Foundation/Slab 3/4/2021 Approved CHARLES POWELL
Deputy Steel/Welding 3/12/2021 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Approval DANIEL DREW
Wood Frame 3/26/2021 Approved DANIEL DREW
Deputy Wood Construction 4/20/2021 Conditional Approval DANIEL ORRANTE
ELECTRICAL-Rough 4/22/2021 Partial Approval CHARLES POWELL
HVAC-Rough 4/22/2021 Approved CHARLES POWELL
PLUMBING-Rough 4/22/2021 Corrections Issued CHARLES POWELL
BUILDING-Rough-Frame 4/28/2021 Corrections Issued JOHN HAYES
Green Building Rough 4/28/2021 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 4/28/2021 Not Ready for Inspection JOHN HAYES
Wood Frame 4/28/2021 Not Ready for Inspection JOHN HAYES
Shower Pan 4/29/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 5/7/2021 Partial Approval CHARLES POWELL
Verify Sprinkler Sign Off 5/7/2021 Approved CHARLES POWELL
Insulation 5/11/2021 Partial Approval CHARLES POWELL
Interior/Exterior Lathing 5/11/2021 Partial Approval CHARLES POWELL
Interior/Exterior Lathing 5/12/2021 Approved MORRIS JACKSON
Special/Order Compliance 5/12/2021 Partial Inspection ALIZAH MAYAGOITIA
Insulation 5/18/2021 Approved CHARLES POWELL
Drywall Nailing 5/20/2021 Approved CHRISTOPHE COCHRAN
Drywall Nailing 5/24/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 9/24/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 9/24/2021 Corrections Issued MISAEL ESPARZA
Final 9/24/2021 Corrections Issued MISAEL ESPARZA
Green Building Final 9/24/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 9/24/2021 Approved MISAEL ESPARZA
HVAC-Final 9/24/2021 Partial Inspection MISAEL ESPARZA
PLUMBING-Final 9/24/2021 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/24/2021 SGSOV Approved MISAEL ESPARZA
Service/Power Release 9/24/2021 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 9/24/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 10/5/2021 Corrections Issued MISAEL ESPARZA
Final 10/5/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 10/5/2021 Approved MISAEL ESPARZA
HVAC-Final 10/5/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 10/5/2021 Approved MISAEL ESPARZA
Service/Power Release 10/5/2021 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 10/5/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/12/2021 Approved MICHEL ABAJAN
Final 10/12/2021 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 10/12/2021 Approved MICHEL ABAJAN
Service/Power Release 10/12/2021 Approved MICHEL ABAJAN