10847 W MORRISON ST 1-4 91601
Certificate Information: 10847 W MORRISON ST 1-4 91601
- Application / Permit
- 20010-20000-02375
- Plan Check / Job No.
- B20VN09244
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (5) Apartment
- Work Description
- (N) 3-STORY TYPE V-B 4-UNIT APT BLDG (TOWNHOME-STYLE) W/ ATTACHED GARAGES (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 10/11/2022
- Issuing Office
- Current Status
- CofO Corrected on 1/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 7/28/2020 | APPLICANT |
| Green Plans Picked Up | 7/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | RODNEY SAMIIAN |
| Corrections Issued | 8/12/2020 | RODNEY SAMIIAN |
| Quality Review Completed | 8/13/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/14/2020 | APPLICANT |
| Refund in Progress | 7/21/2021 | TERENCE SHIA |
| Refund Closed | 7/21/2021 | TERENCE SHIA |
| Applicant returned to address corrections | 9/13/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/23/2022 | NILOOFAR MEHRAIN |
| Issued | 10/11/2022 | APPLICANT |
| CofO in Progress | 10/21/2024 | JOSE AVILA |
| CofO Issued-Status Void | 11/1/2024 | DANIEL ORRANTE |
| Permit Finaled-Status Void | 11/1/2024 | DANIEL ORRANTE |
| Re-Activate Permit | 12/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/30/2025 | RUBEN SALAS |
| CofO Corrected | 1/30/2025 | RUBEN SALAS |
| Permit Finaled | 1/30/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2020 | GABRIEL ROBLES |
| Frnt yard landscape/Water mgmt | Cleared | 11/10/2020 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 11/18/2020 | GABRIEL ROBLES |
| Fire Marshall Fire Life Safety | Cleared | 12/7/2020 | ANDREW KO |
| Low Impact Development | Cleared | 5/24/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/25/2022 | JOSE DUARTE-DIAZ |
| Green Code | Cleared | 6/2/2022 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 6/23/2022 | KURT CORRAL |
| Permit | Cleared | 6/27/2022 | LEE GUILBEAUX |
| Highway dedication | Cleared | 7/11/2022 | JOSE DUARTE-DIAZ |
| DAS Clearance | Cleared | 7/14/2022 | RODNEY SAMIIAN |
Contact Information
| Contractor | Onward Builders Llc; Lic. No.: 1084275-B | 750 N SAN VICENTE BLVD STE 800 WEST HOLLYWOOD, CA 90069 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/9/2023 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 6/9/2023 | Not Ready for Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Corrections Issued | ROBERT DAVIS |
| Piling/Pier/Caisson | 6/12/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Footing/Foundation/Slab | 6/27/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/5/2023 | Approved | DAVID MATSON |
| Piling/Pier/Caisson | 7/5/2023 | Not Ready for Inspection | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2023 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 8/17/2023 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | JOHN HAYES |
| Green Building Rough | 11/14/2023 | Not Ready for Inspection | JOHN HAYES |
| Piling/Pier/Caisson | 11/14/2023 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 11/14/2023 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 11/14/2023 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 11/17/2023 | Corrections Issued | ROBERT GOLD |
| Special/Order Compliance | 11/30/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2023 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2023 | Partial Approval | JOHN HAYES |
| Green Building Rough | 12/26/2023 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 12/26/2023 | Approved | JOHN HAYES |
| Wood Frame | 12/26/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/4/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 1/4/2024 | Approved | JOHN HAYES |
| Wood Frame | 1/4/2024 | Approved | JOHN HAYES |
| Insulation | 1/16/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 1/25/2024 | Approved | JOHN HAYES |
| Special/Order Compliance | 4/11/2024 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 4/24/2024 | Partial Approval | JOHN HAYES |
| Final | 9/11/2024 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 9/11/2024 | Approved | VINCENT HANLEY |
| Green Building Final | 9/11/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 9/11/2024 | Approved | VINCENT HANLEY |
| Special/Order Compliance | 9/11/2024 | Approved | VINCENT HANLEY |
| T-Bar Ceiling | 9/11/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Final | 9/30/2024 | No Access for Inspection | JOSE AVILA |
| Final | 10/18/2024 | OK to Issue CofO | JOSE AVILA |
| Special/Order Compliance | 1/24/2025 | Approved | JUAN VALENZUELA |