10754 N NASSAU AVE 91040
Certificate Information: 10754 N NASSAU AVE 91040
- Application / Permit
- 20010-20000-02366
- Plan Check / Job No.
- B20VN09222
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 26'-10" X 60' (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/23/2021
- Issuing Office
- Current Status
- CofO Issued on 11/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | SELLA BENYAMIN |
| Corrections Issued | 8/26/2020 | SELLA BENYAMIN |
| Quality Review Completed | 8/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/31/2020 | APPLICANT |
| Plan Check Approved | 3/12/2021 | SELLA BENYAMIN |
| Issued | 3/23/2021 | APPLICANT |
| CofO in Progress | 10/12/2023 | WILLIAM WREN |
| Permit Finaled | 11/9/2023 | RUBEN SALAS |
| CofO Issued | 11/9/2023 | RUBEN SALAS |
| Permit Finaled | 11/9/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/1/2020 | GABRIEL ROBLES |
| Permit | Cleared | 10/1/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 10/5/2020 | BRIAN MILLER |
| Sewer availability | Cleared | 10/5/2020 | GABRIEL ROBLES |
| Trees in Parkway | Cleared | 1/28/2021 | JOHN KIM |
| Low Impact Development | Cleared | 2/11/2021 | ANDRES COVARRUBIAS |
| Hydrant and Access approval | Cleared | 2/26/2021 | JEREMY CARTER |
| Roof/Waste drainage to street | Cleared | 3/1/2021 | GABRIEL ROBLES |
| GPI Written Notices | Cleared | 3/12/2021 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/8/2021 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/28/2021 | Approved | MATTHEW NELSON |
| Deputy Reinf. Concrete | 6/15/2021 | Approved | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 11/8/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 11/8/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2022 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 2/8/2022 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/23/2022 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 2/23/2022 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 2/23/2022 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/18/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/18/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 3/18/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/18/2022 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 3/18/2022 | Approved | MATTHEW NELSON |
| Insulation | 4/7/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/7/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/14/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 7/25/2023 | Not Ready for Inspection | WILLIAM WREN |
| Final | 9/19/2023 | No Access for Inspection | WILLIAM WREN |
| Gas Test | 9/19/2023 | Approved | WILLIAM WREN |
| Green Building Final | 9/19/2023 | Corrections Issued | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 9/19/2023 | Approved | WILLIAM WREN |
| Smoke Detectors | 9/19/2023 | Approved | WILLIAM WREN |
| Final | 10/10/2023 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 10/10/2023 | Approved | WILLIAM WREN |