8715 N HERRICK AVE 91352

Certificate Information: 8715 N HERRICK AVE 91352

Application / Permit
20010-20000-02355
Plan Check / Job No.
B20VN09172
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (31'-2 3/4"x 22'-0") IRR SHAPE 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
Permit Issued
Issued on 1/26/2021
Issuing Office
Current Status
CofO Issued on 6/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 TROY DEGUZMAN
Corrections Issued 8/10/2020 TROY DEGUZMAN
Quality Review Completed 8/10/2020 CHON CHIO KUO
Building Plans Picked Up 8/12/2020 APPLICANT
Plan Check Approved 1/25/2021 TROY DEGUZMAN
Issued 1/26/2021 APPLICANT
CofO in Progress 4/21/2022 CHRISTOPHER DELLEFIELD
Permit Finaled 6/16/2022 DANIEL ORRANTE
CofO Issued 6/16/2022 DANIEL ORRANTE
Permit Finaled 6/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/26/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/31/2020 GABRIEL ROBLES
Sewer availability Cleared 8/31/2020 GABRIEL ROBLES
Low Impact Development Cleared 11/18/2020 SARAH YOUSSEF
Hydrant and Access approval Cleared 11/19/2020 MATTHEW CRAIG
Construction near power lines Cleared 12/23/2020 RIDWAN HARDY
Roof/Waste drainage to street Cleared 12/30/2020 ADRIAN CASTRO
Green Code Cleared 1/25/2021 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/3/2021 Approved BEAU COLLINS
Footing/Foundation/Slab 3/8/2021 Approved BEAU COLLINS
Sewer 3/10/2021 Approved BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 3/15/2021 Partial Approval BEAU COLLINS
Deputy Wood Construction 5/18/2021 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 5/24/2021 Partial Approval JOHN HAYES
Green Building Rough 5/24/2021 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 5/24/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/29/2021 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 6/29/2021 Approved MATTHEW NELSON
Green Building Rough 6/29/2021 Approved MATTHEW NELSON
PLUMBING-Rough 6/29/2021 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 6/29/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 7/7/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 7/7/2021 Approved MATTHEW NELSON
HVAC-Rough 7/7/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/7/2021 Approved MATTHEW NELSON
PLUMBING-Rough 7/7/2021 Approved MATTHEW NELSON
Insulation 7/13/2021 Approved MATTHEW NELSON
Drywall Nailing 7/21/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 9/27/2021 Not Ready for Inspection ADAM ESCOTO
Interior/Exterior Lathing 10/22/2021 Partial Inspection WILLIAM KUEHN
Shower Pan 10/22/2021 Approved WILLIAM KUEHN
Final 12/20/2021 Corrections Issued WILLIAM KUEHN
Green Building Final 12/20/2021 Not Ready for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 12/20/2021 SGSOV Not Ready WILLIAM KUEHN
Service/Power Release 12/20/2021 Not Ready for Inspection WILLIAM KUEHN
Smoke Detectors 12/20/2021 Not Ready for Inspection WILLIAM KUEHN
Final 1/21/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 1/21/2022 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/21/2022 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 1/21/2022 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 1/21/2022 Approved MICHEL ABAJAN
Final 2/15/2022 Not Ready for Inspection GREGG CUMMINGS
Green Building Final 2/15/2022 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 2/15/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 4/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 4/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 4/7/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 4/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 4/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Service/Power Release 4/7/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 4/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 4/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Final 4/19/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 4/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 4/19/2022 Approved CHRISTOPHER DELLEFIELD
Service/Power Release 4/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 4/21/2022 Approved CHRISTOPHER DELLEFIELD
Final 4/21/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
HVAC-Final 4/21/2022 Approved CHRISTOPHER DELLEFIELD
Service/Power Release 4/21/2022 Approved CHRISTOPHER DELLEFIELD