8715 N HERRICK AVE 91352
Certificate Information: 8715 N HERRICK AVE 91352
- Application / Permit
- 20010-20000-02355
- Plan Check / Job No.
- B20VN09172
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (31'-2 3/4"x 22'-0") IRR SHAPE 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 1/26/2021
- Issuing Office
- Current Status
- CofO Issued on 6/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | TROY DEGUZMAN |
| Corrections Issued | 8/10/2020 | TROY DEGUZMAN |
| Quality Review Completed | 8/10/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 8/12/2020 | APPLICANT |
| Plan Check Approved | 1/25/2021 | TROY DEGUZMAN |
| Issued | 1/26/2021 | APPLICANT |
| CofO in Progress | 4/21/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 6/16/2022 | DANIEL ORRANTE |
| CofO Issued | 6/16/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/16/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/31/2020 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 11/18/2020 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 11/19/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 12/23/2020 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 12/30/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 1/25/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/3/2021 | Approved | BEAU COLLINS |
| Footing/Foundation/Slab | 3/8/2021 | Approved | BEAU COLLINS |
| Sewer | 3/10/2021 | Approved | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Partial Approval | BEAU COLLINS |
| Deputy Wood Construction | 5/18/2021 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 5/24/2021 | Partial Approval | JOHN HAYES |
| Green Building Rough | 5/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 5/24/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/29/2021 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/29/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 6/29/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/29/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 6/29/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/7/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/7/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/7/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/7/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/7/2021 | Approved | MATTHEW NELSON |
| Insulation | 7/13/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 7/21/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/27/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Interior/Exterior Lathing | 10/22/2021 | Partial Inspection | WILLIAM KUEHN |
| Shower Pan | 10/22/2021 | Approved | WILLIAM KUEHN |
| Final | 12/20/2021 | Corrections Issued | WILLIAM KUEHN |
| Green Building Final | 12/20/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 12/20/2021 | SGSOV Not Ready | WILLIAM KUEHN |
| Service/Power Release | 12/20/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Smoke Detectors | 12/20/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Final | 1/21/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 1/21/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 1/21/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 1/21/2022 | Approved | MICHEL ABAJAN |
| Final | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/7/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/7/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/7/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/7/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 4/7/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 4/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/19/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 4/21/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/21/2022 | Approved | CHRISTOPHER DELLEFIELD |