13930 W WEIDNER ST 91331
Certificate Information: 13930 W WEIDNER ST 91331
- Application / Permit
- 20010-20000-02345
- Plan Check / Job No.
- B20VN09142
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30' X 15' ACCESSORY DWELLING UNIT COMPLY WITH DEPARTMENT ORDER effective date 07/25/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 8/6/2020
- Issuing Office
- Valley
- Current Status
- Issued on 8/6/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2020 | SELLA BENYAMIN |
| Corrections Issued | 7/20/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 7/21/2020 | APPLICANT |
| Issued | 8/6/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 7/23/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 7/23/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 7/23/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/19/2020 | Corrections Issued | JAMES ABREU |
| METHANE-Barrier | 10/19/2020 | Corrections Issued | JAMES ABREU |
| METHANE-Subgrade | 10/19/2020 | Corrections Issued | JAMES ABREU |
| PLUMBING-Rough | 10/19/2020 | Corrections Issued | JAMES ABREU |
| Footing/Foundation/Slab | 1/19/2021 | Approved | JAMES ABREU |
| METHANE-Barrier | 1/19/2021 | Approved | JAMES ABREU |
| METHANE-Subgrade | 1/19/2021 | Approved | JAMES ABREU |
| BUILDING-Rough-Frame | 3/25/2021 | Approved | JAMES ABREU |
| ELECTRICAL-Rough | 3/25/2021 | Approved | JAMES ABREU |
| Green Building Rough | 3/25/2021 | Approved | JAMES ABREU |
| METHANE-Rough | 3/25/2021 | Approved | JAMES ABREU |
| PLUMBING-Rough | 3/25/2021 | Approved | JAMES ABREU |
| Verify Sprinkler Sign Off | 3/25/2021 | Approved | JAMES ABREU |
| Insulation | 4/6/2021 | Approved | JOSEPH BRENEK |
| Interior/Exterior Lathing | 4/6/2021 | Approved | JOSEPH BRENEK |
| Drywall Nailing | 4/15/2021 | Approved | JOSEPH BRENEK |
| Interior/Exterior Lathing | 4/20/2021 | Approved | JOSEPH BRENEK |
| Interior/Exterior Lathing | 5/19/2021 | Approved | JOSEPH BRENEK |
| Final | 7/27/2021 | Corrections Issued | JOSEPH BRENEK |
| Green Building Final | 7/27/2021 | Not Ready for Inspection | JOSEPH BRENEK |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | No Access for Inspection | JOSEPH BRENEK |
| Service/Power Release | 7/27/2021 | Not Ready for Inspection | JOSEPH BRENEK |
| Smoke Detectors | 7/27/2021 | Approved | JOSEPH BRENEK |
| Final | 1/25/2022 | Not Ready for Inspection | JASON BRANNON |
| Green Building Final | 1/25/2022 | Not Ready for Inspection | JASON BRANNON |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Not Ready | JASON BRANNON |
| Service/Power Release | 1/25/2022 | Not Required | JASON BRANNON |
| Final | 1/27/2022 | Conditional Approval | JASON BRANNON |
| Green Building Final | 1/27/2022 | Approved | JASON BRANNON |
| SGSOV-Seismic Gas S/O Valve | 1/27/2022 | SGSOV Approved | JASON BRANNON |