14732 W HESBY ST 91403

Certificate Information: 14732 W HESBY ST 91403

Application / Permit
20010-20000-02344
Plan Check / Job No.
B20VN09133
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (70'8" x 38') 2-STORY SFD/GARAGE FIRE SPRINKLERES NFPA-13D
Permit Issued
Issued on 10/7/2020
Issuing Office
Current Status
CofO Issued on 4/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 MOHAMMAD ESMAILI
Corrections Issued 8/1/2020 MOHAMMAD ESMAILI
Quality Review Completed 8/7/2020 OMID HEDAYAT
Building Plans Picked Up 8/7/2020 APPLICANT
Applicant returned to address corrections 8/21/2020 MOHAMMAD ESMAILI
Applicant returned to address corrections 9/18/2020 MOHAMMAD ESMAILI
Plan Check Approved 10/7/2020 MOHAMMAD ESMAILI
Issued 10/7/2020 APPLICANT
CofO in Progress 4/30/2021 DANIEL ORRANTE
Permit Finaled 4/30/2021 DANIEL ORRANTE
CofO Issued 4/30/2021 DANIEL ORRANTE
Permit Finaled 4/30/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/3/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/4/2020 GUILLERMO PETRA
Sewer availability Cleared 8/4/2020 GUILLERMO PETRA
ZI Cleared 8/14/2020 STEVEN WECHSLER
Permit Cleared 8/19/2020 GUILLERMO PETRA
Low Impact Development Cleared 9/7/2020 MARTIN FRAGOSO
Hydrant and Access approval Cleared 9/10/2020 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 9/15/2020 ADRIAN CASTRO
Trees in Parkway Cleared 9/22/2020 JOHN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/22/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 10/29/2020 Approved CHARLES POWELL
Deputy Wood Construction 11/6/2020 Conditional Approval DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Partial Approval DAVID MATSON
ELECTRICAL-Rough 12/3/2020 Approved CHARLES POWELL
HVAC-Rough 12/3/2020 Approved CHARLES POWELL
PLUMBING-Rough 12/4/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 12/8/2020 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Approved CHARLES POWELL
Green Building Rough 12/8/2020 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 12/8/2020 Not Ready for Inspection CHARLES POWELL
Shower Pan 12/21/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/14/2021 Approved CHARLES POWELL
Green Building Rough 1/14/2021 Not Ready for Inspection CHARLES POWELL
HVAC-Rough 1/14/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 1/14/2021 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 1/14/2021 Approved CHARLES POWELL
Insulation 1/19/2021 Not Ready for Inspection BEAU COLLINS
Interior/Exterior Lathing 1/19/2021 Partial Approval BEAU COLLINS
Insulation 1/21/2021 Approved MATTHEW NELSON
Drywall Nailing 1/27/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 1/28/2021 Approved CHARLES POWELL
Gas Test 2/19/2021 Approved CHARLES POWELL
Deck 2/23/2021 Approved CHARLES POWELL
ELECTRICAL-Final 4/12/2021 Approved MARK JOHNSON
HVAC-Final 4/12/2021 Approved MARK JOHNSON
PLUMBING-Final 4/12/2021 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 4/20/2021 Approved CHARLES POWELL
Final 4/20/2021 Corrections Issued CHARLES POWELL
Green Building Final 4/20/2021 Approved CHARLES POWELL
Green Building Rough 4/20/2021 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved CHARLES POWELL
Service/Power Release 4/20/2021 Approved CHARLES POWELL
Smoke Detectors 4/20/2021 Approved CHARLES POWELL
Final 4/30/2021 OK to Issue CofO DANIEL ORRANTE