10060 N VENA AVE 91331
Certificate Information: 10060 N VENA AVE 91331
- Application / Permit
- 20010-20000-02336
- Plan Check / Job No.
- B20VN09077
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC12.22A33(c)(d) & ENG'R DESIGN
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Current Status
- CofO Issued on 5/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/6/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/10/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/17/2020 | APPLICANT |
| Applicant returned to address corrections | 10/27/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 7/30/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/16/2021 | NILOOFAR MEHRAIN |
| Issued | 8/31/2021 | APPLICANT |
| CofO in Progress | 5/15/2024 | MICHEL ABAJAN |
| Permit Finaled | 5/31/2024 | RUBEN SALAS |
| CofO Issued | 5/31/2024 | RUBEN SALAS |
| Permit Finaled | 5/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/11/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/23/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 3/17/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/25/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 6/29/2021 | CARLOS AGUILERA |
| Green Code | Cleared | 8/16/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/7/2021 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 9/7/2021 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 9/7/2021 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/15/2021 | Approved | MICHEL ABAJAN |
| Wood Frame | 11/9/2021 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 11/23/2021 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 3/11/2022 | Partial Inspection | MICHEL ABAJAN |
| Underground Mechanical | 3/11/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 4/21/2022 | Partial Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 4/21/2022 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Rough | 4/21/2022 | Partial Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 4/21/2022 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 1/24/2023 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 6/15/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/12/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/28/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/28/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/28/2023 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 7/28/2023 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 7/28/2023 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 7/28/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/13/2023 | Partial Inspection | MICHEL ABAJAN |
| Insulation | 9/13/2023 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/13/2023 | Approved | MICHEL ABAJAN |
| Insulation | 9/21/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/4/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/28/2024 | Approved | MICHEL ABAJAN |
| Final | 2/28/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 2/28/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 2/28/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 2/28/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/28/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 2/28/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 2/28/2024 | Approved | MICHEL ABAJAN |
| Final | 4/29/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 4/29/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 5/15/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 5/15/2024 | Approved | MICHEL ABAJAN |