1560 1/2 E HAZELWOOD AVE 90041

Certificate Information: 1560 1/2 E HAZELWOOD AVE 90041

Application / Permit
20010-20000-02326
Plan Check / Job No.
B20VN09037
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 18'2" X 34'11' IRREGULAR SHAPED 2 STORY ACCESSORY DWELLING UNIT PER LAMC12.22.A33(C) AND (E) , ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/19/2022
Issuing Office
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 RARES BODEA
Corrections Issued 8/8/2020 RARES BODEA
Quality Review Completed 8/14/2020 STEVEN KIM
Building Plans Picked Up 8/18/2020 APPLICANT
Applicant returned to address corrections 11/9/2020 RARES BODEA
Applicant returned to address corrections 1/14/2021 RARES BODEA
Applicant returned to address corrections 3/18/2021 RARES BODEA
Plan Check Approved 3/31/2021 RARES BODEA
No Progress 5/6/2021 RARES BODEA
Plan Check Approved 3/22/2022 RARES BODEA
Issued 4/19/2022 APPLICANT
CofO in Progress 2/16/2024 ALIZAH MAYAGOITIA
CofO Issued 2/22/2024 DEROLD HAUFF
Permit Finaled 2/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/9/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 9/9/2020 CECILIO NAVARRO
Sewer availability Cleared 9/9/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 10/15/2020 MATTHEW CRAIG
GPI Written Notices Cleared 1/13/2021 RARES BODEA
Grading Pre-Inspection Cleared 1/13/2021 RARES BODEA
Construction near power lines Cleared 2/12/2021 RIDWAN HARDY
Low Impact Development Cleared 3/2/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/23/2021 ROSA SILVA

Contact Information

Contractor Echelon Construction Llc; Lic. No.: 1022830-B 8431 COLE ST      DOWNEY, CA 90242
Engineer Wang,, Peter Kuo-Ping; Lic. No.: C43144 730 QUAIL VALLEY LANE      WEST COVINA, CA 91791

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/23/2022 Partial Approval RUBEN SALAS
Underground Mechanical 6/3/2022 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/7/2022 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/12/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 10/13/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 10/13/2022 Corrections Issued CRAIG VAUGHAN
Green Building Rough 10/13/2022 Approved CRAIG VAUGHAN
HVAC-Rough 10/13/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 10/13/2022 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 10/13/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 10/19/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 10/19/2022 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Approved CRAIG VAUGHAN
HVAC-Rough 10/19/2022 Approved CRAIG VAUGHAN
Insulation 11/8/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 11/8/2022 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 12/7/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 2/1/2023 Partial Approval KATHRYN BUTTERWORTH
Sewer 4/6/2023 Approved CRAIG VAUGHAN
Underground Mechanical 4/6/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/2/2023 Approved CRAIG VAUGHAN
Service/Power Release 6/2/2023 Not Ready for Inspection CRAIG VAUGHAN
Final 8/10/2023 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 8/10/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/10/2023 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 8/10/2023 Approved CRAIG VAUGHAN
Smoke Detectors 8/10/2023 Not Ready for Inspection CRAIG VAUGHAN
Final 1/18/2024 Corrections Issued CRAIG VAUGHAN
Smoke Detectors 1/18/2024 Approved CRAIG VAUGHAN
Final 1/23/2024 Partial Approval ROY SPAULDING
Gas Test 1/23/2024 Approved ROY SPAULDING
Final 2/15/2024 OK to Issue CofO ALIZAH MAYAGOITIA