18220 W WELBY WAY 91335

Certificate Information: 18220 W WELBY WAY 91335

Application / Permit
20010-20000-02321
Plan Check / Job No.
B20VN09000
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 27'0"X23'4" 2-STORY ADU ADDITION TO (E) 18'0"X20'0" GARAGE
Permit Issued
Issued on 12/15/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 MARVEL DELACRUZ
Corrections Issued 8/4/2020 MARVEL DELACRUZ
Quality Review Completed 8/7/2020 STEVEN KIM
Building Plans Picked Up 8/7/2020 APPLICANT
Applicant returned to address corrections 9/22/2020 MARVEL DELACRUZ
Applicant returned to address corrections 10/6/2020 MARVEL DELACRUZ
Applicant returned to address corrections 11/12/2020 MARVEL DELACRUZ
Plan Check Approved 11/17/2020 MARVEL DELACRUZ
Issued 12/15/2020 APPLICANT
CofO in Progress 9/28/2021 VINCENT HANLEY
Permit Finaled 10/1/2021 MICHAEL SMITH
CofO Issued 10/1/2021 MICHAEL SMITH
Permit Finaled 10/1/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/10/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/11/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/11/2020 JOHN TRIANTAFYLLOS
ZI Cleared 8/11/2020 SARAHI ORTEGA
Green Code Cleared 10/6/2020 MARVEL DELACRUZ
Low Impact Development Cleared 10/9/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 10/15/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 10/30/2020 WALTER RAMIREZ
Construction within easement Cleared 10/30/2020 WALTER RAMIREZ

Contact Information

Contractor S P S Construction; Lic. No.: 683130-B 10153 1/2 RIVERSIDE DR   APT 463    TOLUCA LAKE, CA 91602
Engineer Wyatt,, Lars Wilton; Lic. No.: C85897 405 E 29TH ST APT 5      VANCOUVER, WA 98663

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/23/2020 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 12/29/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Partial Approval VINCENT HANLEY
Green Building Rough 2/11/2021 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/12/2021 Partial Approval VINCENT HANLEY
PLUMBING-Rough 3/5/2021 Not Ready for Inspection VINCENT HANLEY
Sewer 3/5/2021 Approved VINCENT HANLEY
Underground Mechanical 3/5/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Approved VINCENT HANLEY
Wood Frame 3/9/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 3/15/2021 Approved VINCENT HANLEY
HVAC-Rough 3/15/2021 Corrections Issued VINCENT HANLEY
Interior/Exterior Lathing 3/15/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 3/15/2021 Approved VINCENT HANLEY
HVAC-Rough 4/6/2021 Approved VINCENT HANLEY
Insulation 4/6/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/8/2021 Approved VINCENT HANLEY
Drywall Nailing 4/8/2021 Approved VINCENT HANLEY
Green Building Rough 4/8/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/8/2021 Partial Approval VINCENT HANLEY
Drywall Nailing 4/12/2021 Approved VINCENT HANLEY
Green Building Rough 4/12/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/12/2021 Partial Approval VINCENT HANLEY
Shower Pan 4/12/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/22/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 7/19/2021 Corrections Issued DAVID SANDOVAL
HVAC-Final 7/19/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Final 7/19/2021 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Final 9/1/2021 Approved VINCENT HANLEY
Final 9/1/2021 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 9/1/2021 Approved VINCENT HANLEY
Green Building Final 9/1/2021 Approved VINCENT HANLEY
HVAC-Final 9/1/2021 Approved VINCENT HANLEY
PLUMBING-Final 9/1/2021 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/1/2021 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 9/1/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 9/23/2021 Approved VINCENT HANLEY
Final 9/23/2021 Corrections Issued VINCENT HANLEY
HVAC-Final 9/23/2021 Approved VINCENT HANLEY
PLUMBING-Final 9/23/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Approved VINCENT HANLEY
Final 9/28/2021 OK to Issue CofO VINCENT HANLEY