1321 S SPAULDING AVE 90019

Certificate Information: 1321 S SPAULDING AVE 90019

Application / Permit
20010-20000-02307
Plan Check / Job No.
B20VN08972
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ACCESSORY DWELLING UNIT ( 14'-4"x26'-0")
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 3/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 MOHAMMAD ESMAILI
Corrections Issued 8/3/2020 MOHAMMAD ESMAILI
Quality Review Completed 9/4/2020 OMID HEDAYAT
Building Plans Picked Up 9/10/2020 APPLICANT
Plan Check Approved 3/17/2021 MOHAMMAD ESMAILI
Issued 4/22/2021 APPLICANT
CofO in Progress 2/25/2022 JOSE AVILA
Permit Finaled 3/5/2022 DEROLD HAUFF
CofO Issued 3/5/2022 DEROLD HAUFF
Permit Finaled 3/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/21/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/22/2020 THOMAS LANG
Sewer availability Cleared 10/22/2020 THOMAS LANG
Low Impact Development Cleared 10/23/2020 ROBIN YAMADA
CPC Cleared 10/28/2020 MAXFIELD VERMY
ZI Cleared 10/28/2020 MAXFIELD VERMY
Hydrant and Access approval Cleared 11/16/2020 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 11/18/2020 THOMAS LANG

Contact Information

Contractor K B White Construction; Lic. No.: 915958-B 17037 CHATSWORTH STREET   SUITE 203    GRANADA HILLS, CA 91344
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/11/2021 Not Ready for Inspection STUART CHAPMAN
METHANE-Barrier 5/11/2021 Not Ready for Inspection STUART CHAPMAN
METHANE-Subgrade 5/11/2021 Approved STUART CHAPMAN
Underground Mechanical 5/12/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/19/2021 Partial Approval STUART CHAPMAN
METHANE-Barrier 5/19/2021 Partial Approval STUART CHAPMAN
METHANE-Final 5/26/2021 Partial Inspection SCOTT FINNILA
Footing/Foundation/Slab 6/2/2021 Approved RUBEN SALAS
METHANE-Barrier 6/2/2021 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 6/16/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 7/22/2021 Partial Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 7/22/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/22/2021 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Approved JUSTIN HAWLEY
HVAC-Rough 8/9/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 8/9/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/2/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 9/2/2021 Approved SABAS ALONSO
Green Building Rough 9/2/2021 Approved SABAS ALONSO
HVAC-Rough 9/2/2021 Approved SABAS ALONSO
METHANE-Rough 9/2/2021 Approved SABAS ALONSO
Verify Sprinkler Sign Off 9/2/2021 Approved SABAS ALONSO
Insulation 9/13/2021 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 9/13/2021 Approved CALEB MEISTER
Insulation 9/16/2021 Approved CALEB MEISTER
Drywall Nailing 9/22/2021 Approved ASHLEY THOMPSON
Underground Mechanical 10/18/2021 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 11/16/2021 Approved ALIZAH MAYAGOITIA
Underground Mechanical 12/8/2021 Approved JOSE AVILA
Underground Mechanical 12/27/2021 Corrections Issued JOSE AVILA
Underground Mechanical 1/7/2022 Approved JOSE AVILA
Final 1/31/2022 Corrections Issued JOSE AVILA
Green Building Final 1/31/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Approved JOSE AVILA
Service/Power Release 1/31/2022 Approved JOSE AVILA
Smoke Detectors 1/31/2022 Approved JOSE AVILA
Final 2/24/2022 OK to Issue CofO JOSE AVILA