18806 W LULL ST 91335
Certificate Information: 18806 W LULL ST 91335
- Application / Permit
- 20010-20000-02292
- Plan Check / Job No.
- B20VN08908
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 19'-11" X 33'-1" DETACHED 2-STORY ACCESSORY DWELLING UNIT PER ENGINEER
- Permit Issued
- Issued on 11/30/2020
- Issuing Office
- Current Status
- CofO Issued on 6/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 7/27/2020 | JEROME MAGAT PALMA |
| Quality Review Completed | 7/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/29/2020 | APPLICANT |
| Plan Check Approved | 11/12/2020 | JEROME MAGAT PALMA |
| Issued | 11/30/2020 | APPLICANT |
| CofO in Progress | 6/14/2021 | VINCENT HANLEY |
| CofO Issued | 6/15/2021 | MICHAEL SMITH |
| Permit Finaled | 6/15/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2020 | WALLIE JONG |
| Sewer availability | Cleared | 8/17/2020 | WALLIE JONG |
| ZA Case | Cleared | 8/31/2020 | LAUREN PADICK |
| ZA Case | Cleared | 8/31/2020 | LAUREN PADICK |
| ZA Case | Cleared | 8/31/2020 | LAUREN PADICK |
| ZA Case | Cleared | 8/31/2020 | LAUREN PADICK |
| ZA Case | Cleared | 8/31/2020 | LAUREN PADICK |
| ZA Case | Cleared | 8/31/2020 | LAUREN PADICK |
| Miscellaneous | Cleared | 9/1/2020 | LAUREN PADICK |
| Miscellaneous | Cleared | 9/1/2020 | LAUREN PADICK |
| Tract Map conditions | Cleared | 9/1/2020 | LAUREN PADICK |
| Hydrant and Access approval | Cleared | 9/22/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/27/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/2/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/5/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 1/5/2021 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/12/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2021 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2021 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 2/4/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/10/2021 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 2/10/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/10/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/10/2021 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 2/10/2021 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/17/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/17/2021 | Approved | VINCENT HANLEY |
| Insulation | 2/17/2021 | Approved | VINCENT HANLEY |
| Shower Pan | 2/17/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 2/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/16/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 4/16/2021 | Approved | VINCENT HANLEY |
| Final | 6/2/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 6/2/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2021 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 6/2/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 6/2/2021 | Approved | DAVID SCANTLIN |
| Pre-Inspection | 6/8/2021 | No Access for Inspection | DAVID SANDOVAL |
| Final | 6/14/2021 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 6/14/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 6/14/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/14/2021 | Approved | VINCENT HANLEY |
| Service/Power Release | 6/14/2021 | Approved | VINCENT HANLEY |