17324 W MAYALL ST 91325
Certificate Information: 17324 W MAYALL ST 91325
- Application / Permit
- 20010-20000-02283
- Plan Check / Job No.
- B20VN08885
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30' X 42'-3" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 7/16/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 7/21/2021 | JEROME MAGAT PALMA |
| Issued | 7/22/2021 | APPLICANT |
| Building Plans Picked Up | 7/22/2021 | APPLICANT |
| CofO in Progress | 7/24/2025 | NICHOLAS TROWBRIDGE |
| No Progress | 7/31/2025 | RAUL OLAGI |
| CofO in Progress | 7/31/2025 | RAUL OLAGI |
| CofO in Progress | 11/4/2025 | RAUL OLAGI |
| CofO in Progress | 11/4/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 11/18/2025 | RUBEN SALAS |
| CofO Issued | 11/18/2025 | RUBEN SALAS |
| Permit Finaled | 11/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/23/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 11/10/2020 | RIDWAN HARDY |
| Address approval | Cleared | 12/3/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/7/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 7/11/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/14/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/9/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 10/12/2023 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 10/12/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 10/18/2023 | Partial Inspection | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 10/18/2023 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/18/2023 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 11/8/2023 | Approved | JAVIER RAMOS JR |
| Wood Frame | 11/8/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/7/2024 | Corrections Issued | JAVIER RAMOS JR |
| Gas Test | 2/7/2024 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 2/7/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/7/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/7/2024 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 2/7/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/7/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/7/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/7/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/7/2024 | Partial Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/9/2024 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 10/11/2024 | Corrections Issued | JAVIER RAMOS JR |
| Shower Pan | 10/11/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 1/21/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 1/21/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/28/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 7/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 7/18/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 7/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 7/18/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 7/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 7/23/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Service/Power Release | 7/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| Special/Order Compliance | 8/5/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Special/Order Compliance | 8/28/2025 | Corrections Issued | RAUL OLAGI |
| Final | 11/4/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |