7333 N JAMIESON AVE 91335

Certificate Information: 7333 N JAMIESON AVE 91335

Application / Permit
20010-20000-02281
Plan Check / Job No.
B20VN08879
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 16' X 25' DETACHED RECREATION ROOM WITH 1/2 BATHROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 10/29/2020
Issuing Office
Current Status
CofO Issued on 5/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 RAPHAEL ROSAS
Corrections Issued 7/13/2020 RAPHAEL ROSAS
Applicant returned to address corrections 8/17/2020 ROSENDO MEDINA
Plan Check Approved 9/1/2020 RAPHAEL ROSAS
Issued 10/29/2020 APPLICANT
CofO in Progress 5/13/2021 VINCENT HANLEY
Permit Finaled 5/13/2021 JOHN JANSON
CofO Issued 5/13/2021 JOHN JANSON
Permit Finaled 5/13/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/30/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 8/21/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/16/2020 Approved VINCENT HANLEY
Underground Mechanical 11/16/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 12/24/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 12/24/2020 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/24/2020 Approved VINCENT HANLEY
Green Building Rough 12/24/2020 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 12/24/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 2/22/2021 Corrections Issued DAVID SANDOVAL
Green Building Rough 2/22/2021 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 2/25/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 2/25/2021 Approved VINCENT HANLEY
Green Building Rough 2/25/2021 Approved VINCENT HANLEY
HVAC-Rough 2/25/2021 Approved VINCENT HANLEY
PLUMBING-Rough 2/25/2021 Approved VINCENT HANLEY
Insulation 3/5/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/5/2021 Partial Approval VINCENT HANLEY
Drywall Nailing 3/10/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/20/2021 Partial Approval VINCENT HANLEY
Final 4/20/2021 Corrections Issued VINCENT HANLEY
Green Building Final 4/20/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 4/20/2021 Approved VINCENT HANLEY
Smoke Detectors 4/20/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/20/2021 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 5/13/2021 Approved VINCENT HANLEY
Final 5/13/2021 OK to Issue CofO VINCENT HANLEY
Verify Sprinkler Sign Off 5/13/2021 Not Ready for Inspection VINCENT HANLEY